Data center project · Grant County, Washington
H5 Data Centers Quincy (former Intuit and Yahoo buildings)
Operating · H5 runs Quincy data centers it bought from Intuit (2018) and Yahoo (January 2025). Also known as: H5 Quincy I, H5 Quincy II.
- Status
- Operating · as of Jan. 2025
- Location
- Quincy · Grant County
- Power
- Not reported
No power figure in the sources reviewed. - Developer and team
- H5 Data Centers
- Utility
- Grant County PUD
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- July 26, 2026 The Spokesman-Review reported H5 bought Intuit's Quincy data center in 2018 and a Yahoo facility in January 2025, and usually has about 100 workers at its Quincy sites. (The Spokesman-Review, July 26, 2026)
Conflicts and open questions
- The Spokesman-Review also lists Oath as an owner; whether any Yahoo/Oath building in Quincy stayed with Yahoo was not confirmed.
Have records about this project? Send them to tips@signaldata.org.