Data center project · Grant County, Washington
Keel Infrastructure Moses Lake (former Bitfarms mine)
Under construction · A former bitcoin mine in Moses Lake being rebuilt as an AI and high-performance computing data center, under 50 MW. Also known as: Bitfarms Moses Lake.
- Status
- Under construction · as of Sept. 26, 2026
- Location
- Moses Lake · Grant County
- Power
- 18 MW
Energized capacity listed by Keel and reported by Data Center Frontier (under 50 MW). - Land
- 6 acres
- Investment
- $128.742 million turnkey agreement with Vertiv, per Keel's 2025 annual filing as reported.
- Developer and team
- Keel Infrastructure (formerly Bitfarms)
- Utility
- Grant County PUD
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Sept. 26, 2026 Keel posted foundation and duct-bank concrete work at the site. (Keel Infrastructure, Sept. 26, 2026)
- June 1, 2026 A construction stormwater permit for the site took effect, Data Center Frontier reported; commissioning is targeted for 2027 and no tenant has been announced. (Data Center Frontier, Aug. 24, 2026)
- April 27, 2026 Keel said it shut down bitcoin mining and demolished a building at the site. (Keel Infrastructure, Sept. 26, 2026)
Conflicts and open questions
- Under 50 MW; kept because it was found during the review.
Have records about this project? Send them to tips@signaldata.org.