Data center project · King County, Washington
Sabey Tukwila campus expansion (Seattle City Light request)
Withdrawn · Sabey withdrew a 68 MW request to Seattle City Light to expand its Tukwila campus, saying the project was no longer viable.
- Status
- Withdrawn · as of April 30, 2026
- Location
- Sabey's existing Tukwila campus · King County
- Power
- 68 MW
Requested demand, as reported by the Seattle Times. - Developer and team
- Sabey Data Centers
- Utility
- Seattle City Light
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 30, 2026 Sabey withdrew its 68 MW request, the Seattle Times reported; another, unnamed requester had already canceled, and Microsoft and Amazon said that one was not theirs. (The Seattle Times (republished by The Spokesman-Review), May 1, 2026)
Have records about this project? Send them to tips@signaldata.org.