Cloverleaf data center land search, Wrightstown

Paused by moratorium · Cloverleaf tried without success to buy land near Wrightstown; residents voted about 87% against village support for data centers.

← Wisconsin data centers
Adams CountyAshland CountyBarron CountyBayfield CountyBrown CountyBuffalo CountyBurnett CountyCalumet CountyChippewa CountyClark CountyColumbia CountyCrawford CountyDane CountyDodge CountyDoor CountyDouglas CountyDunn CountyEau Claire CountyFlorence CountyFond du Lac CountyForest CountyGrant CountyGreen CountyGreen Lake CountyIowa CountyIron CountyJackson CountyJefferson CountyJuneau CountyKenosha CountyKewaunee CountyLa Crosse CountyLafayette CountyLanglade CountyLincoln CountyManitowoc CountyMarathon CountyMarinette CountyMarquette CountyMenominee CountyMilwaukee CountyMonroe CountyOconto CountyOneida CountyOutagamie CountyOzaukee CountyPepin CountyPierce CountyPolk CountyPortage CountyPrice CountyRacine CountyRichland CountyRock CountyRusk CountySauk CountySawyer CountyShawano CountySheboygan CountySt. Croix CountyTaylor CountyTrempealeau CountyVernon CountyVilas CountyWalworth CountyWashburn CountyWashington CountyWaukesha CountyWaupaca CountyWaushara CountyWinnebago CountyWood CountyCloverleaf data center land search, Wrightstown · Paused by moratorium
Status
Paused by moratorium · as of Aug. 11, 2026
Location
Village of Wrightstown area · Brown County
Status note
No formal proposal; the village paused data center planning and voters rejected the idea in an advisory referendum.
Power
Not reported
No power figure from the developer in the sources reviewed.
Developer and team
Cloverleaf Infrastructure
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Aug. 11, 2026 Voters rejected village support for large data center infrastructure, 1,033 to 151. (NBC 26, Aug. 11, 2026)
  2. June 16, 2026 The village board froze data center zoning and planning work until the referendum was held. (NBC 26, June 16, 2026)
  3. May 27, 2026 Village trustees put an advisory data center question on the August ballot; Cloverleaf confirmed it had tried to buy land in the area. (WFRV Local 5, May 28, 2026)

Have records about this project? Send them to tips@signaldata.org.