Data center project · Columbia County, Wisconsin
Stonebridge data center inquiry, Town of Pacific
Stalled · A $10 billion AI data center floated for the Town of Pacific went quiet after the town chair said any talks would have to be public.
- Status
- Stalled · as of Aug. 3, 2026
- Location
- Town of Pacific, about 35 miles north of Madison · Columbia County
- Status note
- No application; the county says it has not heard from the developer in months.
- Power
- Not reported
No power figure published. - Investment
- About $10 billion (county planning director, November 2025)
- Developer and team
- Stonebridge (Maryland-based real estate developer)
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Aug. 3, 2026 Wisconsin Watch reported, from county emails, that a lawyer for Stonebridge first contacted Columbia County in August 2025; the town chair said the company never followed up once he insisted that any talks happen in public. (Wisconsin Watch, Aug. 3, 2026)
Conflicts and open questions
- Wisconsin Watch identifies the developer as the Maryland-based Stonebridge company that won initial approval for the Fort Meade data center in Florida, the same company as the linked Stonebridge Associates page.