Childersburg Industrial Park hyperscale data center
A developer the mayor called WHP Development is weighing a roughly $6 billion, 500 MW hyperscale campus on 486 city-owned acres at the former World War II munitions site, a Superfund site, in Childersburg. The council changed its zoning in January 2026 to allow data centers, but no sale has closed. Also known as: WHP Development Childersburg.
Who is behind it
The record, newest first
The mayor said the city had sold no property and was waiting on due-diligence results, as residents put up yard signs opposing the project. (ABC 33/40 (WBMA), April 9, 2026)
The mayor said publicly that no decision had been made, the city had sold no land, and any sale would require an ordinance. (ABC 33/40 (WBMA), Feb. 3, 2026; CBS 42 (WIAT), Feb. 2026)
The city council unanimously changed its planned-unit-development zoning so data centers are a principal use; the city's land agreement is in principle, pending the developer's site assessment. (Inside Climate News, Jan. 23, 2026; CBS 42 (WIAT), Feb. 2026)
Conflicts and open questions
- The link between WHP and Western Hospitality Partners is only the reporter's inference; a developer representative would not confirm the company name.
- The site is on the EPA National Priorities List (since 1987), with groundwater study ongoing according to Inside Climate News.
- No update after April 2026 was found.
- Coordinates approximate, in the industrial park area near the Coosa River outside Childersburg.
The full record
- Status note
- The city says no sale is final and it is waiting on the developer's feasibility and due-diligence results.
- Power note
- 500 MW as described by the mayor to Inside Climate News.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)