Data center campus · 165 West Park Loop NW, Huntsville, Madison County, Alabama

Simple Helix Huntsville data center

Operating as of Sept. 9, 2026

Simple Helix runs a multi-tenant colocation data center on West Park Loop in Huntsville, built to Tier III standards. Under 50 MW.

Cite← Alabama data centers
Autauga CountyBaldwin CountyBarbour CountyBibb CountyBlount CountyBullock CountyButler CountyCalhoun CountyChambers CountyCherokee CountyChilton CountyChoctaw CountyClarke CountyClay CountyCleburne CountyCoffee CountyColbert CountyConecuh CountyCoosa CountyCovington CountyCrenshaw CountyCullman CountyDale CountyDallas CountyDeKalb CountyElmore CountyEscambia CountyEtowah CountyFayette CountyFranklin CountyGeneva CountyGreene CountyHale CountyHenry CountyHouston CountyJackson CountyJefferson CountyLamar CountyLauderdale CountyLawrence CountyLee CountyLimestone CountyLowndes CountyMacon CountyMadison CountyMarengo CountyMarion CountyMarshall CountyMobile CountyMonroe CountyMontgomery CountyMorgan CountyPerry CountyPickens CountyPike CountyRandolph CountyRussell CountyShelby CountySt. Clair CountySumter CountyTalladega CountyTallapoosa CountyTuscaloosa CountyWalker CountyWashington CountyWilcox CountyWinston CountySimple Helix Huntsville data center · Operating · 4.5 MW
Power4.5MW reported · stated

Who is behind it

ProjectSimple Helix Huntsville data center
Developer and teamSimple Helix (through Simple Helix LLC)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The company's facility page gives the West Park Loop address and lists 4.5 MW of utility, generator and UPS capacity with 2N+1 power redundancy. (Simple Helix, Sept. 9, 2026)

  2. Simple Helix said it bought NRTC Managed Services' data center and connectivity business, adding to the multi-tenant Huntsville site it already ran. (Simple Helix, Feb. 8, 2021)

  3. Simple Helix announced it had opened a 1.1 MW Tier III data center in Huntsville with two separate data halls. (Simple Helix via PR Newswire, July 14, 2017)

Conflicts and open questions

  • Power figures differ between the 2017 release (1.1 MW) and the current page (4.5 MW); the later figure likely reflects expansion but no source says so.
  • Coordinates approximate for West Park Loop NW.
  • The NRTC deal also added Huntsville operations; whether those are a separate building is not stated.

The full record

Status note
Operator's facility page, last modified Sept. 9, 2026, describes the site in service.
Power note
Facility page lists 4.5 MW each of utility, generator and UPS capacity; the 2017 opening release described a 1.1 MW facility.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.