Data center campus · 1765 Mayfield Drive, Jonesboro, Craighead County, Arkansas

Ritter Communications Data Technology Center

Operating as of Nov. 30, 2020

Ritter Communications runs an $8 million, 8,544-square-foot multi-tenant data center in Jonesboro with 0.75 MW of power, which local reporting called the first provider-grade data center in northeast Arkansas.

Cite← Arkansas data centers
Arkansas CountyAshley CountyBaxter CountyBenton CountyBoone CountyBradley CountyCalhoun CountyCarroll CountyChicot CountyClark CountyClay CountyCleburne CountyCleveland CountyColumbia CountyConway CountyCraighead CountyCrawford CountyCrittenden CountyCross CountyDallas CountyDesha CountyDrew CountyFaulkner CountyFranklin CountyFulton CountyGarland CountyGrant CountyGreene CountyHempstead CountyHot Spring CountyHoward CountyIndependence CountyIzard CountyJackson CountyJefferson CountyJohnson CountyLafayette CountyLawrence CountyLee CountyLincoln CountyLittle River CountyLogan CountyLonoke CountyMadison CountyMarion CountyMiller CountyMississippi CountyMonroe CountyMontgomery CountyNevada CountyNewton CountyOuachita CountyPerry CountyPhillips CountyPike CountyPoinsett CountyPolk CountyPope CountyPrairie CountyPulaski CountyRandolph CountySaline CountyScott CountySearcy CountySebastian CountySevier CountySharp CountySt. Francis CountyStone CountyUnion CountyVan Buren CountyWashington CountyWhite CountyWoodruff CountyYell CountyRitter Communications Data Technology Center · Operating · 0.75 MW
Power0.75MW reported · stated
Floor area8,544sq ft

Who is behind it

ProjectRitter Communications Data Technology Center
Developer and teamRitter Communications
End userMulti-tenant; the operator named Camfil APC and St. Bernards Healthcare as charter customers

The record, newest first

  1. Ritter announced the opening, listing colocation, cloud, disaster recovery and storage services, room for up to 82 racks and N+2 dual-fuel backup power. (Ritter Communications, Nov. 30, 2020; KAIT (Region 8), Dec. 2, 2020)

  2. Ritter broke ground on the facility at its central Jonesboro campus. (Talk Business & Politics, April 30, 2019)

Conflicts and open questions

  • At groundbreaking the size was given as 8,882 sq ft; at opening the operator said 8,544 sq ft.

The full record

Status note
Opened Nov. 30, 2020.
Power note
0.75 MW of power capacity, per the operator.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)