Data center project · Santa Clara County, California
Google 5079-5087 Disk Drive (North San Jose)
Proposed · A 250 MW Google facility the city lists as a 'large energy-use' research site rather than a data center, and the subject of the first CPUC vote on a PG&E data center power agreement. Also known as: H26-005.
- Status
- Proposed · as of Oct. 8, 2026
- Location
- 5079 and 5087 Disk Drive, North San Jose (Alviso) · Santa Clara County
- Status note
- City review at an early stage; the CPUC held its vote on the PG&E service agreement from Oct. 8 to Oct. 29, 2026.
- Power
- 250 MW
250 MW is the transmission-level load in PG&E Advice Letter 7785-E and the figure on the city's list; outlets link the two, but the CPUC summaries read do not name the site. - Floor area
- 483,000 sq ft
- Developer and team
- Google LLC
- Utility
- PG&E (230 kV transmission service)
- Water
- Google says it will use recycled water.
- Incentives
- None reported. The CPUC draft resolution would have Google advance up to about $150 million for network upgrades.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 8, 2026 The CPUC held the draft resolution, which would approve the agreement with added ratepayer protections, to its Oct. 29 meeting. (Stoel Rives, Oct. 14, 2026; California Regulatory Intelligence (calregulatory.com), Sept. 29, 2026; Spectrum News, Oct. 11, 2026)
- Aug. 14, 2026 The CPUC moved its vote on draft Resolution E-5455 from Aug. 13 to Sept. 3; it was later held again to Sept. 17 and Oct. 8. (mgrid.org, Aug. 14, 2026)
- July 10, 2026 San José Spotlight reported plans for up to three buildings of about 483,000 square feet; Google said the site is a chip-engineering lab, not a data center. (San José Spotlight, July 10, 2026)
- March 6, 2026 An application for a 250 MW large energy-use project at 5087 Disk Drive (H26-005) was submitted to the city. (City of San José, Planning Division, undated)
- Dec. 18, 2025 PG&E filed Advice Letter 7785-E seeking approval of an exceptional-case agreement to serve a new 250 MW Google load in San Jose at 230 kV. (mgrid.org, Aug. 14, 2026; Stoel Rives, Oct. 14, 2026)
Conflicts and open questions
- Whether this is a data center is disputed: Google says it is an internal research facility without standard data center backup power; critics and outside experts say the load points to a data center.
- Spectrum News described the draft CPUC terms as $600,000 per MW up front, up to about $150 million.
Have records about this project? Send them to tips@signaldata.org.