Data center project · Santa Clara County, California

Google 5079-5087 Disk Drive (North San Jose)

Proposed · A 250 MW Google facility the city lists as a 'large energy-use' research site rather than a data center, and the subject of the first CPUC vote on a PG&E data center power agreement. Also known as: H26-005.

← California data centers
Alameda CountyAlpine CountyAmador CountyButte CountyCalaveras CountyColusa CountyContra Costa CountyDel Norte CountyEl Dorado CountyFresno CountyGlenn CountyHumboldt CountyImperial CountyInyo CountyKern CountyKings CountyLake CountyLassen CountyLos Angeles CountyMadera CountyMarin CountyMariposa CountyMendocino CountyMerced CountyModoc CountyMono CountyMonterey CountyNapa CountyNevada CountyOrange CountyPlacer CountyPlumas CountyRiverside CountySacramento CountySan Benito CountySan Bernardino CountySan Diego CountySan Francisco CountySan Joaquin CountySan Luis Obispo CountySan Mateo CountySanta Barbara CountySanta Clara CountySanta Cruz CountyShasta CountySierra CountySiskiyou CountySolano CountySonoma CountyStanislaus CountySutter CountyTehama CountyTrinity CountyTulare CountyTuolumne CountyVentura CountyYolo CountyYuba CountyGoogle 5079-5087 Disk Drive (North San Jose) · Proposed · 250 MW
Status
Proposed · as of Oct. 8, 2026
Location
5079 and 5087 Disk Drive, North San Jose (Alviso) · Santa Clara County
Status note
City review at an early stage; the CPUC held its vote on the PG&E service agreement from Oct. 8 to Oct. 29, 2026.
Power
250 MW
250 MW is the transmission-level load in PG&E Advice Letter 7785-E and the figure on the city's list; outlets link the two, but the CPUC summaries read do not name the site.
Floor area
483,000 sq ft
Developer and team
Google LLC
Utility
PG&E (230 kV transmission service)
Water
Google says it will use recycled water.
Incentives
None reported. The CPUC draft resolution would have Google advance up to about $150 million for network upgrades.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 8, 2026 The CPUC held the draft resolution, which would approve the agreement with added ratepayer protections, to its Oct. 29 meeting. (Stoel Rives, Oct. 14, 2026; California Regulatory Intelligence (calregulatory.com), Sept. 29, 2026; Spectrum News, Oct. 11, 2026)
  2. Aug. 14, 2026 The CPUC moved its vote on draft Resolution E-5455 from Aug. 13 to Sept. 3; it was later held again to Sept. 17 and Oct. 8. (mgrid.org, Aug. 14, 2026)
  3. July 10, 2026 San José Spotlight reported plans for up to three buildings of about 483,000 square feet; Google said the site is a chip-engineering lab, not a data center. (San José Spotlight, July 10, 2026)
  4. March 6, 2026 An application for a 250 MW large energy-use project at 5087 Disk Drive (H26-005) was submitted to the city. (City of San José, Planning Division, undated)
  5. Dec. 18, 2025 PG&E filed Advice Letter 7785-E seeking approval of an exceptional-case agreement to serve a new 250 MW Google load in San Jose at 230 kV. (mgrid.org, Aug. 14, 2026; Stoel Rives, Oct. 14, 2026)

Conflicts and open questions

  • Whether this is a data center is disputed: Google says it is an internal research facility without standard data center backup power; critics and outside experts say the load points to a data center.
  • Spectrum News described the draft CPUC terms as $600,000 per MW up front, up to about $150 million.

Have records about this project? Send them to tips@signaldata.org.