Data centers · Santa Clara County, California

Santa Clara County

9 projects on record · 1 moratorium or ban action

← Statewide map
Alameda CountyAlpine CountyAmador CountyButte CountyCalaveras CountyColusa CountyContra Costa CountyDel Norte CountyEl Dorado CountyFresno CountyGlenn CountyHumboldt CountyImperial CountyInyo CountyKern CountyKings CountyLake CountyLassen CountyLos Angeles CountyMadera CountyMarin CountyMariposa CountyMendocino CountyMerced CountyModoc CountyMono CountyMonterey CountyNapa CountyNevada CountyOrange CountyPlacer CountyPlumas CountyRiverside CountySacramento CountySan Benito CountySan Bernardino CountySan Diego CountySan Francisco CountySan Joaquin CountySan Luis Obispo CountySan Mateo CountySanta Barbara CountySanta Clara CountySanta Cruz CountyShasta CountySierra CountySiskiyou CountySolano CountySonoma CountyStanislaus CountySutter CountyTehama CountyTrinity CountyTulare CountyTuolumne CountyVentura CountyYolo CountyYuba CountyGoogle 5079-5087 Disk Drive (North San Jose) · Proposed · 250 MWMicrosoft San Jose Data Center (Alviso) · Under construction · 99 MWSilver Creek Data Center (Prologis) · Proposed · 99 MWMicrosoft San José Data Center 04 (Orchard Parkway) · Proposed · 97.8 MWNorthTown Data Center (Goodman Innovation Centre San Jose) · Proposed · 97.3 MWAmazon Web Services data center (Gilroy) · Under construction180 Park Avenue data center (downtown San José) · Proposed300 S. First Street data center (downtown San José) · Proposed323 Terraine Street data center (San José) · Proposed
Projects in Santa Clara County
Google 5079-5087 Disk Drive (North San Jose)Google LLC250ProposedOct. 8, 202650 MW+
Microsoft San Jose Data Center (Alviso)Microsoft Corporation99Under constructionJune 12, 202650 MW+
Silver Creek Data Center (Prologis)Prologis, L.P.99ProposedJuly 13, 202650 MW+
Microsoft San José Data Center 04 (Orchard Parkway)Microsoft Corporation97.8ProposedOct. 202650 MW+
NorthTown Data Center (Goodman Innovation Centre San Jose)GIC San Jose, LLC97.3ProposedJuly 21, 202650 MW+
180 Park Avenue data center (downtown San José)——ProposedAug. 12, 2025Under 50 MW
300 S. First Street data center (downtown San José)——ProposedOct. 17, 2024Under 50 MW
323 Terraine Street data center (San José)——ProposedApril 9, 2025Under 50 MW
Amazon Web Services data center (Gilroy)Amazon Web Services—Under constructionSept. 14, 2026Under 50 MW

Moratoriums and bans

  1. Sept. 14, 2026 Gilroy: Moratorium. The council unanimously adopted a 45-day urgency moratorium on new data centers, exempting the Amazon building already under construction. (NBC Bay Area, Sept. 14, 2026)

Updates, newest first

  1. Oct. 8, 2026 Google 5079-5087 Disk Drive (North San Jose) · The CPUC held the draft resolution, which would approve the agreement with added ratepayer protections, to its Oct. 29 meeting. (Stoel Rives, Oct. 14, 2026; California Regulatory Intelligence (calregulatory.com), Sept. 29, 2026; Spectrum News, Oct. 11, 2026)
  2. Oct. 2026 Microsoft San José Data Center 04 (Orchard Parkway) · The CEC page and the city list still showed the project under review. (California Energy Commission, undated; City of San José, Planning Division, undated)
  3. Sept. 14, 2026 Amazon Web Services data center (Gilroy) · The City Council adopted a 45-day moratorium on new data centers that excludes the Amazon building under construction. (NBC Bay Area, Sept. 14, 2026)
  4. Sept. 14, 2026 Gilroy: Moratorium · The council unanimously adopted a 45-day urgency moratorium on new data centers, exempting the Amazon building already under construction. (NBC Bay Area, Sept. 14, 2026)
  5. Aug. 14, 2026 Google 5079-5087 Disk Drive (North San Jose) · The CPUC moved its vote on draft Resolution E-5455 from Aug. 13 to Sept. 3; it was later held again to Sept. 17 and Oct. 8. (mgrid.org, Aug. 14, 2026)
  6. July 21, 2026 NorthTown Data Center (Goodman Innovation Centre San Jose) · The CEC issued a notice that it will prepare an environmental impact report for 42 diesel backup generators (25-SPPE-02). (Governor's Office of Land Use and Climate Innovation, CEQAnet, July 21, 2026; California Energy Commission, undated)
  7. July 13, 2026 Silver Creek Data Center (Prologis) · The special use permit application was submitted to the city (SP26-016). (City of San José, Planning Division, undated)
  8. July 10, 2026 Google 5079-5087 Disk Drive (North San Jose) · San José Spotlight reported plans for up to three buildings of about 483,000 square feet; Google said the site is a chip-engineering lab, not a data center. (San José Spotlight, July 10, 2026)
  9. July 9, 2026 Silver Creek Data Center (Prologis) · DCD reported Prologis's plan for a 99 MW, 516,000 sq ft data center. (DatacenterDynamics, July 9, 2026)
  10. June 12, 2026 Microsoft San Jose Data Center (Alviso) · DCD reported Microsoft had broken ground, with completion slated for 2028. (DatacenterDynamics, June 12, 2026)
  11. March 6, 2026 Google 5079-5087 Disk Drive (North San Jose) · An application for a 250 MW large energy-use project at 5087 Disk Drive (H26-005) was submitted to the city. (City of San José, Planning Division, undated)
  12. 2026 Silver Creek Data Center (Prologis) · Prologis applied to the CEC for an exemption for 44 diesel backup generators (26-SPPE-02). (California Energy Commission, undated)
  13. Dec. 18, 2025 Google 5079-5087 Disk Drive (North San Jose) · PG&E filed Advice Letter 7785-E seeking approval of an exceptional-case agreement to serve a new 250 MW Google load in San Jose at 230 kV. (mgrid.org, Aug. 14, 2026; Stoel Rives, Oct. 14, 2026)
  14. Nov. 1, 2025 NorthTown Data Center (Goodman Innovation Centre San Jose) · Baxtel reported Goodman had bought the site and planned two buildings totaling 414,000 sq ft with up to 97.3 MW by 2028. (Baxtel, Nov. 1, 2025)
  15. Aug. 12, 2025 180 Park Avenue data center (downtown San José) · Application submitted; environmental review in progress (PD25-015). (City of San José, Planning Division, undated)
  16. July 2025 Amazon Web Services data center (Gilroy) · The city's community-development director approved the project at staff level after a 2020 application. (The Wall Street Journal (as republished by To Vima), Aug. 10, 2026)
  17. June 30, 2025 NorthTown Data Center (Goodman Innovation Centre San Jose) · An application for an 81-foot data center of about 206,000 sq ft at 350 W. Trimble was filed with the city (CP23-013). (City of San José, Planning Division, undated)
  18. April 9, 2025 Microsoft San Jose Data Center (Alviso) · San José approved the planning application (CP23-016). (City of San José, Planning Division, undated)
  19. April 9, 2025 323 Terraine Street data center (San José) · Application submitted; environmental review in progress (PD25-011). (City of San José, Planning Division, undated)
  20. Oct. 17, 2024 300 S. First Street data center (downtown San José) · Application submitted; environmental review in progress (PD25-013). (City of San José, Planning Division, undated)
  21. Feb. 9, 2023 Microsoft San José Data Center 04 (Orchard Parkway) · The CEC issued a notice of preparation for the project's environmental review (22-SPPE-02). (Governor's Office of Land Use and Climate Innovation, CEQAnet, Feb. 9, 2023)
  22. Nov. 15, 2022 Microsoft San José Data Center 04 (Orchard Parkway) · The city application for two four-story buildings of about 630,000 sq ft was submitted (CP23-008). (City of San José, Planning Division, undated)
  23. July 14, 2022 Microsoft San Jose Data Center (Alviso) · The CEC adopted its decision exempting the project's backup generators from state licensing (19-SPPE-04). (California Energy Commission, undated)

Statewide

No state sales or use tax exemption specific to data centers; SB 58 (2025), a partial exemption for renewable-energy-related equipment, died in the Senate Revenue and Taxation Committee. (Mayer Brown, Dec. 1, 2025) SB 57 (Padilla, 2025), signed Oct. 11, 2025, has the CPUC assess whether new data center load shifts costs to other customers and report by Jan. 1, 2027; AB 93 (2025 water-use estimates) was vetoed. (Mayer Brown, Dec. 1, 2025) Seven bills signed Sept. 21, 2026, mostly effective Jan. 1, 2027: SB 886 and AB 2383 (CPUC data center tariffs so large loads bear their grid and supply costs), SB 1168 (rate-structure review), SB 887 (limits CEQA categorical exemptions for data centers), AB 2469 (water disclosure before local approval), AB 1577 and AB 2619 (energy and water reporting). (KQED, Sept. 21, 2026; The National Law Review (Greenberg Traurig), Oct. 5, 2026) Large-load tariff: PG&E Electric Rule 30 for transmission-level retail customers (CPUC A.24-11-007, filed Nov. 21, 2024); the CPUC partly granted interim use in July 2025, and the proceeding remained open in August 2026. Individual agreements go by advice letter (e.g., Resolution E-5455 for Google, held to Oct. 29, 2026). (California Public Utilities Commission, Aug. 7, 2026; California Public Utilities Commission, June 20, 2025; Mayer Brown, Dec. 1, 2025; Stoel Rives, Oct. 14, 2026) Backup generators of 50-100 MW at data centers go through the California Energy Commission's small power plant exemption (SPPE), with the CEC as CEQA lead agency; most large California data centers appear in its dockets. (California Energy Commission, undated; Union of Concerned Scientists, May 2026) California data centers →