Data center project · Santa Clara County, California
Microsoft San José Data Center 04 (Orchard Parkway)
Proposed · Two four-story Microsoft data center buildings in North San José, still under city and CEC review. Also known as: SJDC 04, CP23-008.
- Status
- Proposed · as of Oct. 2026
- Location
- Orchard Parkway at Component Drive (2549 Orchard Parkway), San José · Santa Clara County
- Power
- 97.8 MW
97.8 MW maximum demand per the CEC. - Floor area
- 631,278 sq ft
- Land
- 22.29 acres
- Developer and team
- Microsoft Corporation
- Utility
- PG&E
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 2026 The CEC page and the city list still showed the project under review. (California Energy Commission, undated; City of San José, Planning Division, undated)
- Feb. 9, 2023 The CEC issued a notice of preparation for the project's environmental review (22-SPPE-02). (Governor's Office of Land Use and Climate Innovation, CEQAnet, Feb. 9, 2023)
- Nov. 15, 2022 The city application for two four-story buildings of about 630,000 sq ft was submitted (CP23-008). (City of San José, Planning Division, undated)
Conflicts and open questions
- Filed before 2024; kept because review is still open. Matching the city file CP23-008 to the CEC project is by location and size.
Have records about this project? Send them to tips@signaldata.org.