Gemstone Technology Park
A 620-acre data center campus on farmland at the south edge of Kuna, rezoned for light industry in 2025 and still in early development while neighbors' challenge to the approval is on appeal. Also known as: Diode Ventures Kuna data center, Gemstone Technology Park LLC.
Who is behind it
The record, newest first
The developer's project page still described Gemstone Technology Park as an early-stage, proposed data center site. (Diode Ventures, Oct. 27, 2026)
The petitioners appealed to the Idaho Supreme Court, as reported. (BoiseDev, Aug. 19, 2026)
The district judge denied the petition for judicial review, as reported. (BoiseDev, Aug. 19, 2026)
Neighboring landowners asked a district court to review the approval, arguing it was procedurally flawed because one council member should not have voted; the city defended the approval, and the landowner and the developer asked to join its defense. (BoiseDev, Feb. 10, 2026)
The council moved its written decision on the cases to May 20, 2025. (City of Kuna City Council, May 6, 2025)
The City Council approved the rezone 3-2, with the mayor breaking a tie, as reported. (BoiseDev, April 4, 2025)
Kuna's Planning and Zoning Commission held its hearing on the comprehensive plan map amendment and rezone (Cases 24-01-CPM and 24-01-ZC) and recommended approval. (City of Kuna Planning and Zoning Commission, Jan. 2025; BoiseDev, Jan. 29, 2025)
Conflicts and open questions
- A guest opinion column estimated the campus's demand at 600 to 800 MW; that figure is not from a record or the developer and is not used.
- The Supreme Court appeal's case number and status were not checked in court records.
The full record
- Status note
- Kuna's City Council approved the comprehensive plan map change and rezone on a split vote in April 2025 and scheduled its written decision for May 20, 2025; a court challenge to the approval was on appeal at the Idaho Supreme Court as of August 2026, and the developer describes the project as in early development. No construction reported.
- Power note
- Size not reported: neither the city record reviewed nor the developer gives a power figure.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)