Lex Developments AI data center, Pocatello (Project IV West)
A proposed $2.6 billion AI data center of seven 100,000-square-foot buildings on 49 acres at an idled Pocatello industrial plant, denied by the city in 2026. Also known as: Project IV West, former Hoku Materials plant data center.
Who is behind it
The record, newest first
The City Council voted 4-1 to uphold the denial; the developer said it would appeal. (EastIdahoNews.com, July 16, 2026; BoiseDev, July 20, 2026)
The city hearing examiner held a public hearing on the conditional use permit; about 90 people testified, about 60 of them opposed, as reported. (BoiseDev, May 14, 2026; EastIdahoNews.com, May 15, 2026)
The hearing examiner denied the permit, finding the application did not show the project would not harm public health, safety or welfare; the developer appealed to the City Council. (BoiseDev, June 10, 2026)
Idaho Power wrote that the project would add more than 100 MW of load, as reported. (BoiseDev, May 14, 2026)
Conflicts and open questions
- The city's own hearing examiner decision and council record were not pulled; the project is sourced to reporting.
- Square footage is the sum of seven 100,000-square-foot buildings as reported.
The full record
- Status note
- Pocatello's hearing examiner denied the conditional use permit in May 2026, and the City Council upheld the denial 4-1 on July 16, 2026; the developer said it would appeal to district court. Whether an appeal was filed was not checked.
- Power note
- As reported, a February 2026 Idaho Power letter described a load increase of more than 100 MW, expected by 2031.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)