Data center project · McCracken County, Kentucky
Paducah Site AI campus (DOE, Brookfield, NextEra)
Proposed · A DOE partnership to build a 1.8 GW AI campus and 2 GW of new gas generation on part of the uranium enrichment site under cleanup. Also known as: Paducah Gaseous Diffusion Plant.
- Status
- Proposed · as of July 29, 2026
- Location
- DOE Paducah Site (former Paducah Gaseous Diffusion Plant), west of Paducah · McCracken County
- Status note
- DOE selected the partners; the power service agreement still needs PSC approval.
- Power
- 1,800 MW
1.8 GW AI and high-performance computing campus (DOE); 2 GW of new gas generation and up to 2.6 GW of batteries are separate. - Investment
- More than $100 billion, privately funded (DOE)
- Developer and team
- Brookfield; NextEra Energy (power generation)
- Utility
- Big Rivers Electric (wholesale), Jackson Purchase Energy Cooperative (retail), Paducah Power System (partner)
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- July 30, 2026 AP reported that construction was expected to finish in 2031 and that a newly formed local group questioned the plans, citing the lack of an independent impact study. (Associated Press (via News4JAX), July 30, 2026)
- July 29, 2026 DOE announced the partnership, about 8,000 construction jobs and 600 permanent jobs, with NextEra to build and own the dedicated power. (U.S. Department of Energy, July 29, 2026)