Data center campus · Servistar Industrial Way and Ampad Way, Westfield, Hampden County, Massachusetts

Servistar data center campus (Westfield)

Denied as of Oct. 13, 2026

A 10-building hyperscale campus on roughly 150 to 162 industrial acres in Westfield, permitted in 2021 but never started, lost its bid to extend its special permit in October 2026 amid local opposition. Also known as: Westfield Data Center Campus, Servistar Data Center.

Cite← Massachusetts data centers
Barnstable CountyBerkshire CountyBristol CountyDukes CountyEssex CountyFranklin CountyHampden CountyHampshire CountyMiddlesex CountyNantucket CountyNorfolk CountyPlymouth CountySuffolk CountyWorcester CountyServistar data center campus (Westfield) · Denied · 274 MW
Power274MW reported · stated
Floor area2.7e+06sq ft
Site162acres

Who is behind it

ProjectServistar data center campus (Westfield)Also: Westfield Data Center Campus, Servistar Data Center
Developer and teamServistar Realties LLC
End userNot identified

The record, newest first

  1. At a special meeting, the planning board voted unanimously against extending the 2021 special permit, finding no good cause; members cited the company's lapsed LLC registration and the permit never being recorded at the registry of deeds. (New England Public Media (via Connecticut Public), Oct. 14, 2026; The Boston Globe, Oct. 14, 2026)

  2. The City Council gave final approval to a one-year moratorium on new data centers; the already permitted Servistar project was treated as exempt. (The Reminder, July 16, 2026; New England Public Media (via Connecticut Public), Oct. 14, 2026; The Boston Globe, July 14, 2026)

  3. One of the proposed lots, 191 Servistar Industrial Way, was sold to a local buyer who told The Shoestring he had not known it was part of the project. (The Shoestring, July 2, 2026)

  4. The state House adopted an amendment adding a data center sales tax exemption meant to help the Westfield project, but the economic development bill stalled that summer. (The Reminder, Aug. 11, 2022)

  5. The City Council approved a 40-year tax agreement for Servistar Realties, 10 to 3. (The Westfield News, Oct. 23, 2021)

  6. A $2.7 billion, roughly 2.7 million square foot data center campus of about 10 buildings in a Westfield industrial park entered permitting. (IREI, Aug. 26, 2021)

Conflicts and open questions

  • The planning board met in a special session on Tuesday, Oct. 13, 2026, per NEPM's Oct. 14 report.
  • The Westfield News reports the Oct. 21, 2021, tax agreement vote as 10-3; the Boston Globe reports a 9-3 city vote approving the project in 2021. They may be different votes.
  • Acreage: 162 acres (Westfield News, 2021) vs. more than 150 acres (NEPM, 2026). NEPM says Servistar never bought the land.
  • Possible appeal: Servistar had 20 days under state law to appeal the denial; no appeal was found as of Oct. 24, 2026.

The full record

Status note
The planning board unanimously refused to extend the 2021 special permit, which runs out at the end of October 2026; the developer had 20 days to appeal.
Power note
274 MW at full build-out per the Boston Globe; The Shoestring says the buildings would carry 18 to 42 MW of critical IT load. The figures conflict and may measure different things.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.