Baltimore County
1 project on record · 1 moratorium or ban action
← Statewide map| Security Land Baltimore Data Center (Woodlawn) | Security Land and Development LP | 150 | Paused by moratorium | Sept. 22, 2026 | 50 MW+ |
Moratoriums and bans
- Sept. 22, 2026 Baltimore County: Moratorium. The council, which suspended new data center permits in early 2026 while its planning board studied rules, voted unanimously to extend the pause through the end of 2027. (WMAR-2 News, May 7, 2026; WYPR, Sept. 22, 2026)
Updates, newest first
- Sept. 22, 2026 Security Land Baltimore Data Center (Woodlawn) · The Baltimore County Council unanimously extended its data center moratorium through the end of 2027. (WYPR, Sept. 22, 2026)
- Sept. 22, 2026 Baltimore County: Moratorium · The council, which suspended new data center permits in early 2026 while its planning board studied rules, voted unanimously to extend the pause through the end of 2027. (WMAR-2 News, May 7, 2026; WYPR, Sept. 22, 2026)
- Dec. 5, 2025 Security Land Baltimore Data Center (Woodlawn) · FOX45 reported a plan for a data center of up to 150 MW on 42 acres in Woodlawn, with five acres to go to BGE for a substation; the county said only a demolition permit had been filed. (FOX45 News (WBFF), Dec. 5, 2025; DatacenterDynamics, Dec. 10, 2025)
Statewide
Chapter 640 of 2020 exempts equipment bought for a qualified data center from the state sales and use tax (the operator must invest at least $5 million, or $2 million in a Tier I area, and create at least five jobs) and lets counties and towns reduce or remove property tax on data center equipment; a 2026 bill to repeal both (HB 560) was introduced. (Maryland Department of Legislative Services, 2026; Maryland General Assembly, Oct. 25, 2026) The Critical Infrastructure Streamlining Act of 2024 (Chapter 411, SB 474) exempts on-site emergency backup generators at qualifying data centers from the Public Service Commission's certificate of public convenience and necessity under set conditions; it also changes how corporate income tax from certain new data centers is distributed. (Maryland General Assembly, May 9, 2024) SB 116 of 2025 (enacted over the governor's veto as Chapter 10 of the 2025 special session) requires a state study of data centers' environmental, energy and economic impacts, due Sept. 1, 2026; Frederick County said in mid-September that it had not yet been completed. (Maryland Department of Legislative Services, 2025; Maryland General Assembly, Oct. 25, 2026; Frederick County Executive, Sept. 14, 2026) The Next Generation Energy Act of 2025 required each utility to file a separate large-load rate schedule by Sept. 1, 2026 so other customers do not carry the cost of serving them; the Utility RELIEF Act (HB 1532, Chapter 353 of 2026) lowered the large-load threshold from 100 MW to 25 MW, ordered a Public Service Commission registry of large loads by July 1, 2027, and barred data centers in most Baltimore City tax increment financing districts. (Maryland Department of Legislative Services, 2026; Maryland General Assembly, Oct. 25, 2026) Maryland data centers →