Data center campus · Farmland northeast of U.S. 63 and Paris Road, Columbia, Boone County, Missouri

Proposed technology hub rezoning, US 63 and Paris Road, Columbia

Denied as of Nov. 2025

A rezoning that the owner said could allow a data center on 63 acres northeast of U.S. 63 and Paris Road failed on a 3-3 Columbia council vote in November 2025.

Cite← Missouri data centers
Adair CountyAndrew CountyAtchison CountyAudrain CountyBarry CountyBarton CountyBates CountyBenton CountyBollinger CountyBoone CountyBuchanan CountyButler CountyCaldwell CountyCallaway CountyCamden CountyCape Girardeau CountyCarroll CountyCarter CountyCass CountyCedar CountyChariton CountyChristian CountyClark CountyClay CountyClinton CountyCole CountyCooper CountyCrawford CountyDade CountyDallas CountyDaviess CountyDeKalb CountyDent CountyDouglas CountyDunklin CountyFranklin CountyGasconade CountyGentry CountyGreene CountyGrundy CountyHarrison CountyHenry CountyHickory CountyHolt CountyHoward CountyHowell CountyIron CountyJackson CountyJasper CountyJefferson CountyJohnson CountyKnox CountyLaclede CountyLafayette CountyLawrence CountyLewis CountyLincoln CountyLinn CountyLivingston CountyMacon CountyMadison CountyMaries CountyMarion CountyMcDonald CountyMercer CountyMiller CountyMississippi CountyMoniteau CountyMonroe CountyMontgomery CountyMorgan CountyNew Madrid CountyNewton CountyNodaway CountyOregon CountyOsage CountyOzark CountyPemiscot CountyPerry CountyPettis CountyPhelps CountyPike CountyPlatte CountyPolk CountyPulaski CountyPutnam CountyRalls CountyRandolph CountyRay CountyReynolds CountyRipley CountySaline CountySchuyler CountyScotland CountyScott CountyShannon CountyShelby CountySt. Charles CountySt. Clair CountySt. Francois CountySt. Louis CountySt. Louis (city) CountySte. Genevieve CountyStoddard CountyStone CountySullivan CountyTaney CountyTexas CountyVernon CountyWarren CountyWashington CountyWayne CountyWebster CountyWorth CountyWright CountyProposed technology hub rezoning, US 63 and Paris Road, Columbia · Denied
PowerNot statedNot reported in the records found
Site63acres

Who is behind it

ProjectProposed technology hub rezoning, US 63 and Paris Road, Columbia
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. After a 7-2 planning commission recommendation, the council's rezoning vote failed 3-3. (Columbia Missourian (via KBIA), Nov. 19, 2025)

  2. The owner asked to rezone the land to industrial, saying a data center may be pursued there; a city agenda report backed the request. (KBIA, Oct. 8, 2025)

Conflicts and open questions

  • Below scope thresholds (63 acres, no MW); kept because it is a denied, contested request that preceded Columbia's 2026 data center rules.
  • No developer company named; the owner is a private individual.

The full record

Status note
The council's vote on rezoning from agricultural to industrial failed 3-3.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.