Data center campus · Hunt Midwest Business Center, NE Parvin Road, Kansas City (Northland), Clay County, Missouri

Google Kansas City Data Center (Hunt Midwest Business Center)

Under construction as of Feb. 12, 2026

Google is building a $1 billion data center on about 315 acres at Hunt Midwest Business Center off NE Parvin Road in Kansas City's Northland, announced in March 2024. Also known as: Project Shale, Shalerock LLC.

Cite← Missouri data centers
Adair CountyAndrew CountyAtchison CountyAudrain CountyBarry CountyBarton CountyBates CountyBenton CountyBollinger CountyBoone CountyBuchanan CountyButler CountyCaldwell CountyCallaway CountyCamden CountyCape Girardeau CountyCarroll CountyCarter CountyCass CountyCedar CountyChariton CountyChristian CountyClark CountyClay CountyClinton CountyCole CountyCooper CountyCrawford CountyDade CountyDallas CountyDaviess CountyDeKalb CountyDent CountyDouglas CountyDunklin CountyFranklin CountyGasconade CountyGentry CountyGreene CountyGrundy CountyHarrison CountyHenry CountyHickory CountyHolt CountyHoward CountyHowell CountyIron CountyJackson CountyJasper CountyJefferson CountyJohnson CountyKnox CountyLaclede CountyLafayette CountyLawrence CountyLewis CountyLincoln CountyLinn CountyLivingston CountyMacon CountyMadison CountyMaries CountyMarion CountyMcDonald CountyMercer CountyMiller CountyMississippi CountyMoniteau CountyMonroe CountyMontgomery CountyMorgan CountyNew Madrid CountyNewton CountyNodaway CountyOregon CountyOsage CountyOzark CountyPemiscot CountyPerry CountyPettis CountyPhelps CountyPike CountyPlatte CountyPolk CountyPulaski CountyPutnam CountyRalls CountyRandolph CountyRay CountyReynolds CountyRipley CountySaline CountySchuyler CountyScotland CountyScott CountyShannon CountyShelby CountySt. Charles CountySt. Clair CountySt. Francois CountySt. Louis CountySt. Louis (city) CountySte. Genevieve CountyStoddard CountyStone CountySullivan CountyTaney CountyTexas CountyVernon CountyWarren CountyWashington CountyWayne CountyWebster CountyWorth CountyWright CountyGoogle Kansas City Data Center (Hunt Midwest Business Center) · Under construction
PowerNot statedNot reported in the records found
Floor area1.435e+06sq ft
Site315acres

Who is behind it

ProjectGoogle Kansas City Data Center (Hunt Midwest Business Center)Also: Project Shale, Shalerock LLC
Developer and teamGoogle (through Shalerock LLC)
End userGoogle

The record, newest first

  1. Reporting on Google's second campus said this first Missouri campus, begun in 2024, was still under construction. (KCTV5, Feb. 12, 2026)

  2. Google announced a $1 billion data center at Hunt Midwest Business Center, with Evergy supplying power and a 400 MW solar purchase (Beavertail Solar) for new carbon-free supply. (Hunt Midwest, March 20, 2024; Startland News, March 20, 2024)

  3. Google filed plans for up to 1.435 million sq ft of data center space on 315 acres, and later received approval. (DCD, Jan. 10, 2024)

  4. Google, through Shalerock LLC, was reported to have bought 236.4 acres north of Hunt Midwest, adding to 78.9 acres bought in 2019, for a $600 million proposal code-named Project Shale. (DCD, Dec. 20, 2021)

Conflicts and open questions

  • The 400 MW figure is the solar contract's generating capacity, not the data center's load; no load figure is published.
  • The 2021 bond figure ($25 billion) is from DCD only; the Port KC record was not opened.
  • Coordinates are approximate, placed in the business park along NE Parvin Road.

The full record

Status note
Google broke ground in 2024; reporting in Feb. 2026 said the campus was still under construction.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.