Google Project Mica (Northland, I-435 and US 169)
Google is building a five-building, roughly 1.56 million sq ft data center campus on about 500 acres in Kansas City's Northland in Clay County, financed through up to $10 billion in Port KC bonds. Also known as: Project Mica, Rocky Branch Creek Technology Park (earlier Diode Ventures plan).
Who is behind it
The record, newest first
Google confirmed it is the company behind Project Mica, said it will pay the full energy costs under an Evergy agreement, and said it will qualify for Evergy's large-load tariff. (KCTV5, Feb. 12, 2026; Axios Kansas City, Feb. 12, 2026; DCD, Feb. 2026)
The Port KC Board of Commissioners voted 6-0 to authorize up to $10 billion in taxable revenue bonds for Project Mica. (Port KC, July 28, 2025; KCTV5, July 29, 2025)
Port KC's development committee took up a resolution authorizing bonds for Project Mica and recommended up to $10 billion with a 25-year, 75% property tax abatement. (Port KC, April 14, 2025; DCD, April 15, 2025; Ingram's, April 15, 2025)
County records showed a Google affiliate, AG Rose Solutions LLC, bought about 493 acres from Diode Ventures in December 2023; QTS had earlier let its contract on the land lapse over power availability. (DCD, Jan. 10, 2024)
Diode Ventures proposed the Rocky Branch Creek Technology Park on 359 acres northeast of US 169 and I-435, with up to nine buildings and about 215-220 MW of IT load. (DCD, April 26, 2022)
Conflicts and open questions
- The lead grouped Meta Kansas City buildings 4 and 5 and a 'Meta Kansas City expansion' with this campus; those belong to Meta's separate Golden Plains campus southwest of US 169 and NW 128th St.
- KCTV5 placed the site 'in Smithville'; the reported address is a Kansas City (Northland) address on N. Arrowhead Trafficway; Smithville School District receives workforce funds.
- Coordinates are approximate, placed northeast of the I-435/US 169 interchange near the reported address.
- DCD's Feb. 2026 article calls this Google's second Kansas City campus; the first is at Hunt Midwest Business Center (separate record).
The full record
- Status note
- Google confirmed the campus in Feb. 2026 while crews were on site; reporting says construction is under way.
- Power note
- Axios reports up to 500 MW at full capacity; DCD and Axios cite Port KC materials referring to about 700 MW of substation capacity (Nashua and on-site substations). Range 500-700 MW.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)