Google Montgomery County data center (Project Spade)
Google is building a $15 billion data center campus south of I-70 near New Florence, which the county gave a Chapter 100 personal property tax abatement in June 2026. Also known as: Project Spade.
Who is behind it
Related Digital
The record, newest first
The Columbia Missourian reported Google building its data center on the opposite side of I-70 from Amazon's. (Columbia Missourian (via Griffon News), Aug. 27, 2026)
The county commission unanimously approved a Chapter 100 incentive package with personal property tax abatement only. (KOMU 8 (via KBIA), June 11, 2026)
DCD tied the campus to developer Related Digital: 934 acres, two buildings of about 800,000 sq ft in total, and construction expected to start in 2026. (DCD, May 2026)
Gov. Kehoe and Google announced a $15 billion data center in Montgomery County, with Ameren Missouri as utility partner. (Office of Missouri Gov. Mike Kehoe, May 20, 2026; KOMU 8 (via St. Louis Public Radio), May 21, 2026)
DCD reported a separate filing for Project Spade by a New York LLC, covering about 780 acres in the county and 130 acres in New Florence. (DCD, Jan. 15, 2026)
Conflicts and open questions
- Separate campus from Amazon's Project Green, which sits north of I-70 east of New Florence; together they cover about 1,900 acres (Columbia Missourian).
- Acreage: about 910 acres in DCD's January 2026 report (780 county + 130 city) vs. 934 acres in its May 2026 report.
- DCD's May article date is inferred as May 2026 from the announcement; the page did not show a dateline when opened.
- Commission vote date (June 8, 2026) inferred from KOMU's June 11 report of a 'Monday' vote.
- Jobs: the state cites hundreds of operations jobs; KOMU reported Google expects about 300 workers.
The full record
- Status note
- KOMU described the campus as under construction in June 2026 and the Columbia Missourian said Google was building it in August 2026; no completion date is public.
- Power note
- DCD reports the campus targets 1.2 GW; neither Google's nor the governor's release states the campus load, so mw is left blank. Google says it has contracted over 1 GW of new generation in Missouri and is backing 500+ MW more through Ameren.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)