Data center campus · Rifle Range Road, north of Marshfield (outside city limits), Webster County, Missouri

Lumon Solutions high-performance computing facility, Marshfield

Under construction as of June 16, 2026

A small modular computing facility on five acres north of Marshfield drew packed public meetings and led Webster County to adopt a six-month moratorium, which the county says will not stop this site.

Cite← Missouri data centers
Adair CountyAndrew CountyAtchison CountyAudrain CountyBarry CountyBarton CountyBates CountyBenton CountyBollinger CountyBoone CountyBuchanan CountyButler CountyCaldwell CountyCallaway CountyCamden CountyCape Girardeau CountyCarroll CountyCarter CountyCass CountyCedar CountyChariton CountyChristian CountyClark CountyClay CountyClinton CountyCole CountyCooper CountyCrawford CountyDade CountyDallas CountyDaviess CountyDeKalb CountyDent CountyDouglas CountyDunklin CountyFranklin CountyGasconade CountyGentry CountyGreene CountyGrundy CountyHarrison CountyHenry CountyHickory CountyHolt CountyHoward CountyHowell CountyIron CountyJackson CountyJasper CountyJefferson CountyJohnson CountyKnox CountyLaclede CountyLafayette CountyLawrence CountyLewis CountyLincoln CountyLinn CountyLivingston CountyMacon CountyMadison CountyMaries CountyMarion CountyMcDonald CountyMercer CountyMiller CountyMississippi CountyMoniteau CountyMonroe CountyMontgomery CountyMorgan CountyNew Madrid CountyNewton CountyNodaway CountyOregon CountyOsage CountyOzark CountyPemiscot CountyPerry CountyPettis CountyPhelps CountyPike CountyPlatte CountyPolk CountyPulaski CountyPutnam CountyRalls CountyRandolph CountyRay CountyReynolds CountyRipley CountySaline CountySchuyler CountyScotland CountyScott CountyShannon CountyShelby CountySt. Charles CountySt. Clair CountySt. Francois CountySt. Louis CountySt. Louis (city) CountySte. Genevieve CountyStoddard CountyStone CountySullivan CountyTaney CountyTexas CountyVernon CountyWarren CountyWashington CountyWayne CountyWebster CountyWorth CountyWright CountyLumon Solutions high-performance computing facility, Marshfield · Under construction
PowerNot statedNot reported in the records found
Site5acres

Who is behind it

ProjectLumon Solutions high-performance computing facility, Marshfield
Developer and teamLumon Solutions
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The county adopted a six-month moratorium but said it does not intend to use it to halt the project under construction. (Webster County, Missouri, June 16, 2026)

  2. DCD identified Lumon Solutions as developer of an eight-unit modular facility. (DatacenterDynamics, May 18, 2026)

  3. Hundreds of residents attended a county commission meeting asking for a moratorium; the county hired outside counsel to review its authority. (KY3, May 11, 2026)

  4. Webster County said it learned of the project from social media and described a 5-acre, roughly 70x200 ft facility with closed-loop cooling and no incentive request. (Webster County, Missouri, May 6, 2026)

Conflicts and open questions

  • Under 50 MW (no MW reported; 5-acre site, eight modular units). Kept because it is contested and confirmed.
  • KY3 (Sept. 2026) reports that the developer suing Benton County over its moratorium (NSI6 LLC) is also behind the Rifle Range Road site, and that the same company is suing Springfield over its moratorium for a site at 2900 S. National Ave.

The full record

Status note
Webster County said the site was under construction and that its June 2026 moratorium is not intended to halt it.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)