Data center campus · About 7 miles north of Jamestown, next to an Otter Tail Power substation, Stutsman County, North Dakota

Applied Digital Jamestown hosting facility

Operating as of Oct. 7, 2026

Applied Digital's first data center, a 106 MW crypto-mining hosting site north of Jamestown that has operated since February 2022. Also known as: Applied Blockchain Jamestown, APLD Hosting.

Cite← North Dakota data centers
Adams CountyBarnes CountyBenson CountyBillings CountyBottineau CountyBowman CountyBurke CountyBurleigh CountyCass CountyCavalier CountyDickey CountyDivide CountyDunn CountyEddy CountyEmmons CountyFoster CountyGolden Valley CountyGrand Forks CountyGrant CountyGriggs CountyHettinger CountyKidder CountyLaMoure CountyLogan CountyMcHenry CountyMcIntosh CountyMcKenzie CountyMcLean CountyMercer CountyMorton CountyMountrail CountyNelson CountyOliver CountyPembina CountyPierce CountyRamsey CountyRansom CountyRenville CountyRichland CountyRolette CountySargent CountySheridan CountySioux CountySlope CountyStark CountySteele CountyStutsman CountyTowner CountyTraill CountyWalsh CountyWard CountyWells CountyWilliams CountyApplied Digital Jamestown hosting facility · Operating · 106 MW
Power106MW reported · record
Floor area65,000sq ft
Site40acres

Who is behind it

ProjectApplied Digital Jamestown hosting facilityAlso: Applied Blockchain Jamestown, APLD Hosting
Developer and teamApplied Digital (through APLD Hosting LLC)
End userCrypto-mining (bitcoin) hosting customers

The record, newest first

  1. Applied Digital reported the 106 MW Jamestown facility operating at full capacity as of Aug. 31, 2026. (Applied Digital Corporation (SEC Form 10-Q), Oct. 7, 2026)

  2. The company held a formal opening of the 100 MW Jamestown facility, with 83 MW online and the rest due in the second quarter of 2022. (Applied Blockchain, Inc., May 10, 2022)

  3. A company official told the Jamestown Stutsman Development Corp. annual meeting that the site had eight buildings of about 65,000 sq ft and could grow to 200 MW. (The Jamestown Sun, April 2022)

  4. Applied Digital brought its first Jamestown hosting facility online after construction began in September 2021. (Applied Digital Corporation (SEC Form 10-K), Aug. 2, 2023)

Conflicts and open questions

  • Coordinates approximate, placed about 7 miles north of Jamestown as reported; not a parcel address.
  • Crypto-mining (bitcoin) hosting facility; operating before 2024, included as an operating campus.
  • The FY2026 10-K says the hosting segment has one customer with about 18 months left on its contract; the energy services agreement commitment runs about 0.4 more years as of Aug. 31, 2026.
  • The planned expansion to 200 MW was not confirmed in later filings, which still report 106 MW.

The full record

Status note
Applied Digital reported the 106 MW facility running at full capacity as of Aug. 31, 2026, serving one crypto-mining customer.
Power note
Opened as a 100 MW facility; later reported as 105 to 106 MW. A separate GPU building, announced at 5 MW in December 2022 and later increased to 9 MW, was planned next to it.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.