Flatwater Free Press reported Google's self-reported water consumption at its Nebraska data centers rose to about 732 million gallons in 2025. (Flatwater Free Press, July 8, 2026)
Google put its 2024 Nebraska spending at $930 million and its five-year total at about $4.4 billion, saying all three Nebraska sites were still growing. (Nebraska Examiner (via KRVN), Nov. 30, 2024)
At the Papillion site, Google announced at least $750 million more for Nebraska, including additions to the Papillion campus and a new data center in northwest Omaha. (Nebraska Examiner (via KMTV 3 News Now), April 21, 2022)
Google said its $600 million data center at Highway 50 and Schram Road was under construction and should open within 18 to 24 months; OPPD had been discussing power needs with the company for about six years. (KMTV 3 News Now, Oct. 4, 2019)
Conflicts and open questions
- Water figures are Google's own reports for all of its Nebraska data centers together, not for this campus alone.
The full record
- Status note
- Google said in late 2024 that the Papillion campus, its first in Nebraska, was still expanding.
- Power note
- No power figure in the sources reviewed.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)