Data center project · Storey County, Nevada
Vantage Data Centers NV11
Approved · A Vantage colocation site in Storey County with state abatements and a large-load utility contract pending.
- Status
- Approved · as of June 3, 2026
- Location
- Southeast corner of Electric Avenue and USA Parkway, Storey County (GOED application) · Storey County
- Power
- Not reported
No figure in the sources reviewed. - Developer and team
- Vantage Data Centers NV11, LLC
- Utility
- NV Energy (Sierra Pacific Power)
- Incentives
- $11,531,616 in GOED tax abatements approved March 21, 2024 (10 jobs at $59.62 an hour, growing to 27; $150 million capital equipment)
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- June 3, 2026 NV Energy asked the PUCN to approve a large-load service contract with Vantage Data Centers NV11 (docket 26-05028). (Public Utilities Commission of Nevada, Oct. 20, 2026)
- July 16, 2025 DCD reported state filings showed NV11 starting operations by the fourth quarter of 2026. (DCD, July 16, 2025)
- March 21, 2024 The GOED board approved $11,531,616 in abatements for Vantage Data Centers NV11, LLC for a colocation facility at Electric Avenue and USA Parkway. (Governor's Office of Economic Development, March 21, 2024; Governor's Office of Economic Development, March 21, 2024)
Conflicts and open questions
- DCD reported that state filings targeted Q4 2026 for NV11 and placed NV11 and NV12 at 100 and 200 Electric Avenue; whether NV11 is part of Vantage's NV1 campus is not stated by any source.