Data center campus · 5109 Hayden Run Road (between Britton Parkway and I-270), Hilliard, Franklin County, Ohio

AWS Hilliard Hayden Run data center campus

Operating as of Sept. 20, 2023

Amazon's first Hilliard data center campus, on Hayden Run Road between Britton Parkway and I-270, was built in phases starting in 2015 and was counted as operating in 2023. Also known as: AWS Britton Parkway campus, Vadata Hilliard.

Cite← Ohio data centers
Adams CountyAllen CountyAshland CountyAshtabula CountyAthens CountyAuglaize CountyBelmont CountyBrown CountyButler CountyCarroll CountyChampaign CountyClark CountyClermont CountyClinton CountyColumbiana CountyCoshocton CountyCrawford CountyCuyahoga CountyDarke CountyDefiance CountyDelaware CountyErie CountyFairfield CountyFayette CountyFranklin CountyFulton CountyGallia CountyGeauga CountyGreene CountyGuernsey CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHighland CountyHocking CountyHolmes CountyHuron CountyJackson CountyJefferson CountyKnox CountyLake CountyLawrence CountyLicking CountyLogan CountyLorain CountyLucas CountyMadison CountyMahoning CountyMarion CountyMedina CountyMeigs CountyMercer CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyMorrow CountyMuskingum CountyNoble CountyOttawa CountyPaulding CountyPerry CountyPickaway CountyPike CountyPortage CountyPreble CountyPutnam CountyRichland CountyRoss CountySandusky CountyScioto CountySeneca CountyShelby CountyStark CountySummit CountyTrumbull CountyTuscarawas CountyUnion CountyVan Wert CountyVinton CountyWarren CountyWashington CountyWayne CountyWilliams CountyWood CountyWyandot CountyAWS Hilliard Hayden Run data center campus · Operating
PowerNot statedNot reported in the records found

Who is behind it

ProjectAWS Hilliard Hayden Run data center campusAlso: AWS Britton Parkway campus, Vadata Hilliard
Developer and teamAmazon Web Services (through Vadata Inc.)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The Dispatch counts three operating Amazon data centers in Hilliard. (The Columbus Dispatch (via Yahoo Finance), Sept. 20, 2023)

  2. Local reporting says building on the first Hilliard site east of Britton Parkway, under way since 2015, has recently wrapped up. (The Hilliard Beacon, April 23, 2023)

  3. Ohio officials sign off on Amazon's data center plans; Hilliard's package for the first phase includes a property tax abatement valued at about $5.4 million. (Data Center Knowledge, Feb. 27, 2015)

Conflicts and open questions

  • Coordinates from a Census geocode of 5109 Hayden Run Road.
  • Data Center Dynamics gives 5109 Hayden Run as Amazon's first Hilliard campus, with work beginning in 2015, the AWS Ohio region launching in 2016 and a third building begun in November 2019.
  • No MW figure found in any record.

The full record

Status note
The Dispatch (Sept. 2023, citing a data center listing site) counted three operating Amazon data centers in Hilliard; the Hilliard Beacon reported in April 2023 that construction on this first site had recently wrapped up.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.