Data center campus · 8565-8619 Industrial Parkway, Jerome Township (Marysville mailing address), Union County, Ohio

AWS Jerome Township Industrial Parkway data center campus

Under construction as of Dec. 1, 2025

Amazon's multi-building campus on Industrial Parkway in Jerome Township was still under construction in 2025, when a fire at one building sent workers for smoke treatment.

Cite← Ohio data centers
Adams CountyAllen CountyAshland CountyAshtabula CountyAthens CountyAuglaize CountyBelmont CountyBrown CountyButler CountyCarroll CountyChampaign CountyClark CountyClermont CountyClinton CountyColumbiana CountyCoshocton CountyCrawford CountyCuyahoga CountyDarke CountyDefiance CountyDelaware CountyErie CountyFairfield CountyFayette CountyFranklin CountyFulton CountyGallia CountyGeauga CountyGreene CountyGuernsey CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHighland CountyHocking CountyHolmes CountyHuron CountyJackson CountyJefferson CountyKnox CountyLake CountyLawrence CountyLicking CountyLogan CountyLorain CountyLucas CountyMadison CountyMahoning CountyMarion CountyMedina CountyMeigs CountyMercer CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyMorrow CountyMuskingum CountyNoble CountyOttawa CountyPaulding CountyPerry CountyPickaway CountyPike CountyPortage CountyPreble CountyPutnam CountyRichland CountyRoss CountySandusky CountyScioto CountySeneca CountyShelby CountyStark CountySummit CountyTrumbull CountyTuscarawas CountyUnion CountyVan Wert CountyVinton CountyWarren CountyWashington CountyWayne CountyWilliams CountyWood CountyWyandot CountyAWS Jerome Township Industrial Parkway data center campus · Under construction
PowerNot statedNot reported in the records found

Who is behind it

ProjectAWS Jerome Township Industrial Parkway data center campus
Developer and teamAmazon Web Services (through Amazon Data Services, Inc.)
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Business First (via New Project Media) reports the AWS campus at 8619 Industrial Parkway is under development, with four buildings and at least one under construction. (New Project Media, Dec. 1, 2025)

  2. Township adopts a nine-month moratorium on new data centers; existing Amazon projects are not halted. (WOSU 89.7 NPR News (via WYSU), Sept. 9, 2025)

  3. An HVAC-unit fire at the Amazon building under construction at 8565 Industrial Parkway leaves five people with smoke inhalation. (Marysville Journal-Tribune, April 17, 2025)

  4. Jerome Township trustees unanimously approve an enterprise zone agreement with a 10-year, 100% abatement plus a donation agreement for an Amazon data facility. (Marysville Journal-Tribune, Nov. 20, 2019)

  5. Union County's Community Improvement Corporation approves an agreement for Amazon Data Services to build a 250,000 sq ft, $200 million data center in Jerome Township (site not named in the article excerpt). (Marysville Journal-Tribune, Nov. 14, 2019)

Conflicts and open questions

  • Coordinates from a Census geocode of 8619 Industrial Parkway (Plain City mailing address).
  • A 2019 Amazon project in Jerome Township ($200 million, 250,000 sq ft) may be this campus, but the records do not name Industrial Parkway.
  • The trustee vote date (Nov. 19, 2019) comes from a Nov. 20 report of a Tuesday vote.

The full record

Status note
A building was under construction during an April 2025 fire; Business First (via New Project Media, Dec. 2025) describes the campus as under development with at least one building under construction.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.