AWS Jerome Township Industrial Parkway data center campus
Amazon's multi-building campus on Industrial Parkway in Jerome Township was still under construction in 2025, when a fire at one building sent workers for smoke treatment.
Who is behind it
The record, newest first
Business First (via New Project Media) reports the AWS campus at 8619 Industrial Parkway is under development, with four buildings and at least one under construction. (New Project Media, Dec. 1, 2025)
Township adopts a nine-month moratorium on new data centers; existing Amazon projects are not halted. (WOSU 89.7 NPR News (via WYSU), Sept. 9, 2025)
An HVAC-unit fire at the Amazon building under construction at 8565 Industrial Parkway leaves five people with smoke inhalation. (Marysville Journal-Tribune, April 17, 2025)
Jerome Township trustees unanimously approve an enterprise zone agreement with a 10-year, 100% abatement plus a donation agreement for an Amazon data facility. (Marysville Journal-Tribune, Nov. 20, 2019)
Union County's Community Improvement Corporation approves an agreement for Amazon Data Services to build a 250,000 sq ft, $200 million data center in Jerome Township (site not named in the article excerpt). (Marysville Journal-Tribune, Nov. 14, 2019)
Conflicts and open questions
- Coordinates from a Census geocode of 8619 Industrial Parkway (Plain City mailing address).
- A 2019 Amazon project in Jerome Township ($200 million, 250,000 sq ft) may be this campus, but the records do not name Industrial Parkway.
- The trustee vote date (Nov. 19, 2019) comes from a Nov. 20 report of a Tuesday vote.
The full record
- Status note
- A building was under construction during an April 2025 fire; Business First (via New Project Media, Dec. 2025) describes the campus as under development with at least one building under construction.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)