AWS Sunbury data center campus
Sunbury granted Amazon a 30-year tax break in 2024 for a planned $2 billion campus in its new industrial park; the city adopted a data center moratorium in April 2026 and voters face a proposed data center ban in November.
Who is behind it
The record, newest first
Council unanimously certifies a citizen-proposed charter amendment prohibiting data center construction to the Nov. 3, 2026 ballot. (1808Delaware, July 16, 2026)
Residents circulate petitions for a charter amendment barring data centers above 25 MW. (NBC4 WCMH-TV, June 25, 2026)
City council unanimously adopts a moratorium on establishing data centers in the city, running through Jan. 31, 2027. (WOSU 89.7 NPR News, April 16, 2026)
Mayor calls for a moratorium on data center projects; coverage ties the 330-acre rezoning to an Amazon campus of about 200 acres. (1808Delaware, March 26, 2026)
Planning and Zoning Commission hearing on Sunbury 37 LLC's request to zone more than 330 acres near AWS's site as limited industrial is pushed to March 23 to verify parcel numbers. (1808Delaware, Feb. 23, 2026)
Coverage details a 450,000 sq ft first building, construction starting January 2028 and the first building in service by December 2034; AWS is negotiating power terms with AEP Ohio. (1808Delaware, Nov. 25, 2024)
Sunbury City Council approves a CRA incentive for Amazon Data Services' $2 billion campus in the Sunbury Business and Technology Park, with 50 committed jobs. (City of Sunbury, Nov. 21, 2024; 1808Delaware, Nov. 25, 2024)
Conflicts and open questions
- Coordinates from a Census geocode of 11793 Vans Valley Road (Galena mailing address), the site address reported by 1808Delaware.
- Acreage unresolved: 10TV reports Amazon would occupy about 200 of the park's acres; the pending rezoning covers 330+ acres; WOSU gives the park as 1,200 acres and the city about 1,300.
- Whether the moratorium applies to AWS's already-incentivized project is not stated in the records.
- Outcome of the 330-acre rezoning hearing set for March 23, 2026 was not found in the records.
The full record
- Status note
- Sunbury's data center moratorium (adopted April 15, 2026, through Jan. 31, 2027) covers new data centers in the city; whether it reaches AWS's already-incentivized project is not stated. A citizen charter amendment prohibiting data center construction is on the Nov. 3, 2026 ballot.
- Floor area note
- first building
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)