Bristolville 25 Lordstown data center proposal
A developer's $3.6 billion plan for four three-story data center buildings on 133 acres off Route 45 stalled after Lordstown adopted a moratorium and the Ohio Supreme Court ruled the village did not have to review its site plan.
Who is behind it
The record, newest first
The Ohio Supreme Court unanimously held the village had no legal duty to proceed with the site plan review because no zoning permit application had been completed. (WKBN, Oct. 20, 2026)
Council approved another 180-day extension of the moratorium, effective July 5, carrying it to about January 2027. (WKBN, Oct. 20, 2026; The Vindicator, June 17, 2026)
After reversing an earlier ban on AI data centers in December 2025, village council approved a 180-day data center moratorium (January 2026). (WKBN, June 25, 2026)
The developer and BHGH Properties asked the Ohio Supreme Court to order the village to review the site plan under pre-moratorium rules (filed November 2025). (WKBN, June 25, 2026)
Bristolville 25 Developer LLC applied for site plan review of a $3.6 billion data center on 133 acres; an Oct. 28 letter from its attorney offered to cover about $10.8 million of village water upgrades not funded by state grants. (Business Journal Daily, Oct. 29, 2025)
Conflicts and open questions
- Coordinates approximate: SR 45 corridor in Lordstown; no street address published.
- Site spans Trumbull and Mahoning counties (Lordstown and North Jackson / Jackson Township) per Business Journal Daily and WKBN; listed under Trumbull.
- WKBN (Oct. 2026) describes four three-story data center buildings on industrially zoned land.
The full record
- Status note
- Ohio Supreme Court ruled Oct. 20, 2026 that the village need not review the site plan; village data center moratorium extended to January 2027.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)