Proposed as of Sept. 24, 2026

Texas-based Corscale has proposed a $2.9 billion, 312 MW campus on roughly 162 acres annexed into southeast Canton, which must still pass the city's new data center review rules.

Cite← Ohio data centers
Adams CountyAllen CountyAshland CountyAshtabula CountyAthens CountyAuglaize CountyBelmont CountyBrown CountyButler CountyCarroll CountyChampaign CountyClark CountyClermont CountyClinton CountyColumbiana CountyCoshocton CountyCrawford CountyCuyahoga CountyDarke CountyDefiance CountyDelaware CountyErie CountyFairfield CountyFayette CountyFranklin CountyFulton CountyGallia CountyGeauga CountyGreene CountyGuernsey CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHighland CountyHocking CountyHolmes CountyHuron CountyJackson CountyJefferson CountyKnox CountyLake CountyLawrence CountyLicking CountyLogan CountyLorain CountyLucas CountyMadison CountyMahoning CountyMarion CountyMedina CountyMeigs CountyMercer CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyMorrow CountyMuskingum CountyNoble CountyOttawa CountyPaulding CountyPerry CountyPickaway CountyPike CountyPortage CountyPreble CountyPutnam CountyRichland CountyRoss CountySandusky CountyScioto CountySeneca CountyShelby CountyStark CountySummit CountyTrumbull CountyTuscarawas CountyUnion CountyVan Wert CountyVinton CountyWarren CountyWashington CountyWayne CountyWilliams CountyWood CountyWyandot CountyCorscale Midwest Digital Gateway · Proposed · 312 MW
Power312MW reported · stated
Site162acres

Who is behind it

ProjectCorscale Midwest Digital Gateway
Developer and teamCorscale
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Trade reporting identified Corscale as developer of the Midwest Digital Gateway, a proposed 312 MW, $2.9 billion campus on about 162 acres, with Amazon Web Services a possible but unconfirmed tenant. (Construction Review Online, Sept. 24, 2026)

  2. Canton City Council passed, 8-3, an ordinance defining data centers and setting development standards for them. (Spectrum News 1, July 28, 2026)

  3. Local reporting said Canton had annexed two potential data center sites from Canton Township in late 2025, including a 162.9-acre farm parcel southeast of Millerton Street and Central Avenue SE bought in 2025 by companies with data center ties. (Massillon Independent (via AOL), April 6, 2026)

Conflicts and open questions

  • Coordinates approximate: Millerton St SE / Central Ave SE area, southeast Canton.
  • Acreage differs: about 162 or 163.5 acres annexed in the same article, and 162.9 acres in the April Massillon Independent story; that story does not name Corscale, but the acreage and location match.
  • Evidence is reporting only; no city annexation ordinance or site plan has been cited yet.
  • Separate from the Panattoni ~100-acre, 324 MW East Side Canton proposal reported by Ideastream/WYSU on 2026-08-19 (former Ford forge site), which is not one of my leads.

The full record

Power note
Reported planned capacity.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.