A developer group led by Logistix Property Group, which holds a development agreement with Hamilton, has proposed a data center on 29 acres at 1380 University Boulevard, drawing resident concerns in fall 2025. Also known as: Wharton Cincy DC.

Cite← Ohio data centers
Adams CountyAllen CountyAshland CountyAshtabula CountyAthens CountyAuglaize CountyBelmont CountyBrown CountyButler CountyCarroll CountyChampaign CountyClark CountyClermont CountyClinton CountyColumbiana CountyCoshocton CountyCrawford CountyCuyahoga CountyDarke CountyDefiance CountyDelaware CountyErie CountyFairfield CountyFayette CountyFranklin CountyFulton CountyGallia CountyGeauga CountyGreene CountyGuernsey CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHighland CountyHocking CountyHolmes CountyHuron CountyJackson CountyJefferson CountyKnox CountyLake CountyLawrence CountyLicking CountyLogan CountyLorain CountyLucas CountyMadison CountyMahoning CountyMarion CountyMedina CountyMeigs CountyMercer CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyMorrow CountyMuskingum CountyNoble CountyOttawa CountyPaulding CountyPerry CountyPickaway CountyPike CountyPortage CountyPreble CountyPutnam CountyRichland CountyRoss CountySandusky CountyScioto CountySeneca CountyShelby CountyStark CountySummit CountyTrumbull CountyTuscarawas CountyUnion CountyVan Wert CountyVinton CountyWarren CountyWashington CountyWayne CountyWilliams CountyWood CountyWyandot CountyHamilton Innovation Center (Logistix) data center proposal · Proposed · 100 MW
Power100MW reported · stated
Site29acres

Who is behind it

ProjectHamilton Innovation Center (Logistix) data center proposalAlso: Wharton Cincy DC
Developer and teamLogistix Property Group
Wharton Equity (through Wharton Cincy DC, LLC)
LightHouse
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Residents raised concerns at a council meeting; the city called the $100 million project very early, and the mayor said no vote would be taken. (WCPO 9 Cincinnati, Oct. 9, 2025)

  2. Hamilton was weighing a data center on 29 acres at 1380 University Boulevard, led by Wharton Cincy DC, a Wharton Equity-Logistix joint venture. (Hoodline, Sept. 11, 2025)

Conflicts and open questions

  • Coordinates approximate, near the University Boulevard address.
  • No 2026 status found; 100+ MW rests on the developer's website estimate.

The full record

Status note
City described the project as in very early stages; feasibility studies under way and city and state approvals still needed as of Oct. 2025. No 2026 activity found.
Power note
WCPO: Logistix's website estimates 100+ MW; the city said it was too early to size the project.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)