Data center campus · New Albany, Franklin County, Ohio

STACK Infrastructure NAL01 campus

Operating as of June 16, 2026

STACK lists a two-building, 60 MW colocation campus on 40 acres in New Albany, built around an existing data center it bought in 2019. Also known as: NAL01A, NAL01B.

Cite← Ohio data centers
Adams CountyAllen CountyAshland CountyAshtabula CountyAthens CountyAuglaize CountyBelmont CountyBrown CountyButler CountyCarroll CountyChampaign CountyClark CountyClermont CountyClinton CountyColumbiana CountyCoshocton CountyCrawford CountyCuyahoga CountyDarke CountyDefiance CountyDelaware CountyErie CountyFairfield CountyFayette CountyFranklin CountyFulton CountyGallia CountyGeauga CountyGreene CountyGuernsey CountyHamilton CountyHancock CountyHardin CountyHarrison CountyHenry CountyHighland CountyHocking CountyHolmes CountyHuron CountyJackson CountyJefferson CountyKnox CountyLake CountyLawrence CountyLicking CountyLogan CountyLorain CountyLucas CountyMadison CountyMahoning CountyMarion CountyMedina CountyMeigs CountyMercer CountyMiami CountyMonroe CountyMontgomery CountyMorgan CountyMorrow CountyMuskingum CountyNoble CountyOttawa CountyPaulding CountyPerry CountyPickaway CountyPike CountyPortage CountyPreble CountyPutnam CountyRichland CountyRoss CountySandusky CountyScioto CountySeneca CountyShelby CountyStark CountySummit CountyTrumbull CountyTuscarawas CountyUnion CountyVan Wert CountyVinton CountyWarren CountyWashington CountyWayne CountyWilliams CountyWood CountyWyandot CountySTACK Infrastructure NAL01 campus · Operating · 60 MW
Power60MW reported · stated
Floor area448,000sq ft
Site40acres

Who is behind it

ProjectSTACK Infrastructure NAL01 campusAlso: NAL01A, NAL01B
Developer and teamSTACK Infrastructure
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. STACK's location page lists NAL01A (116,000 sq ft) and NAL01B (332,000 sq ft) on a 40-acre campus with 60 MW of critical capacity. (STACK Infrastructure, June 16, 2026)

  2. STACK buys an existing Tier III data center in New Albany from an unnamed Ohio company, with 17 acres for future development. (Data Center Frontier, Oct. 16, 2019)

Conflicts and open questions

  • Coordinates approximate, in New Albany; no street address appears in any source.
  • County not confirmed: New Albany spans Franklin and Licking counties; Franklin is assumed from the approximate coordinates only.
  • Building MW figures (11 + 51) exceed the 60 MW campus total; STACK notes some figures are rounded.

The full record

Status note
STACK's location page (last updated June 16, 2026) lists two buildings with capacity figures; Data Center Frontier reported in 2019 that STACK bought an existing Tier III data center in New Albany with 17 acres for expansion. The page does not say whether NAL01B is finished.
Power note
60 MW critical capacity, including 48 MW of new capacity (operator). Building figures: NAL01A 11 MW, NAL01B 51 MW.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)