Strata Expanse AI Center of Excellence
Strata Expanse began building a self-powered AI computing site west of Hanging Rock in late 2025 on land bought from the county development corporation, drawing questions from Ironton officials and residents.
Who is behind it
The record, newest first
The company had not released requested power figures; it said it would create 200 to 300 jobs. The county economic development corporation sold it the land. (The Herald-Dispatch, Jan. 20, 2026)
Ironton City Council held a special meeting where members questioned the county economic development corporation's director about the project, which lies outside city limits. (The Herald-Dispatch, Jan. 20, 2026)
Strata Expanse and partners announced the AI Center of Excellence with a ribbon-cutting; work had begun about three weeks earlier on a roughly 10 MW site, expandable to 80 MW, using on-site hydrogen, solar, geothermal, natural gas and battery power. (The Herald-Dispatch, Dec. 20, 2025; WOWK 13 News, Dec. 19, 2025)
Conflicts and open questions
- Under 50 MW as built; kept because a confirmed project with stated expansion to 80 MW.
- Coordinates approximate: west of Hanging Rock on CR 1A.
The full record
- Status note
- Construction began about late November 2025 per the Herald-Dispatch; no later status found.
- Power note
- About 10 MW of computing, expandable to 80 MW, per the Herald-Dispatch. Under 50 MW at present.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)