Thor Equities Urbana Technology Hub
Urbana first rezoned land for Thor Equities' 460,000-square-foot campus, then reversed itself, and the developer is now suing the city in federal court. Also known as: Urbana Technology Hub.
Who is behind it
The record, newest first
Thor sued the city, its council and its zoning appeals board in U.S. District Court for the Southern District of Ohio. (WYSO, June 23, 2026; Data Center Dynamics, undated)
Council unanimously passed Ordinance 4635-26, restoring the pre-2025 code and removing data centers as a permitted M-1 use. (Peak of Ohio, June 17, 2026)
Thor bought nearly 100 more acres next to the site. (WDTN, June 15, 2026)
Council passed a 12-month emergency moratorium on new data centers. (WYSO, June 23, 2026; Data Center Dynamics, undated)
Thor submitted a site plan; the Building and Zoning Board of Appeals rejected it (February 2026). (WYSO, June 23, 2026)
Council approved a Community Reinvestment Area tax abatement agreement with Thor (November 2025). (WYSO, June 23, 2026)
Council allowed data processing uses in M-1 districts and annexed and rezoned Thor's land to M-1 (April 2025). (WYSO, June 23, 2026)
Conflicts and open questions
- Coordinates approximate: SR 55 / US 68 area near the Rittal plant.
- Acreage: DCD says about 230; WDTN reports 133 acres bought in 2025 plus about 100 in June 2026.
The full record
- Status note
- Site plan rejected, 12-month moratorium (March 2026), data centers removed as permitted M-1 use (June 16, 2026); developer sued in federal court June 19, 2026.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)