Data center campus · Unincorporated Grady County near Amber, Grady County, Oklahoma

Aligned Data Centers campus near Amber

Proposed as of Sept. 28, 2026

Aligned Data Centers bought about 850 acres near Amber in mid-2026 for a campus powered largely on site. Local officials say they have little authority to stop it.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyAligned Data Centers campus near Amber · Proposed
PowerNot statedNot reported in the records found
Site850acres

Who is behind it

ProjectAligned Data Centers campus near Amber
Developer and teamAligned Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Aligned scheduled a public meeting at Amber-Pocasset High School. (KGOU / OPMX, Sept. 30, 2026)

  2. Commissioners voted not to ask voters to create a county planning commission; counsel had said at the Sept. 8 meeting that a county cannot adopt a moratorium. (KGOU / OPMX, Sept. 30, 2026)

  3. Amber's town council voted to cancel plans to annex the land around the site. (The Frontier, Sept. 23, 2026; KGOU / OPMX, Sept. 30, 2026)

  4. News 9 reported the site at about 800 acres, with closed-loop cooling and no construction yet. (News 9, Sept. 18, 2026)

  5. Grady County commissioners held a special meeting on the project at the county courthouse. (KSWO, Sept. 2, 2026)

  6. Aligned bought about 850 acres near Amber for about $17 million. (The Frontier, Sept. 23, 2026)

Conflicts and open questions

  • The Frontier gives about 850 acres; News 9 gives 800. No capacity has been reported. The Frontier said construction could start as early as December 2026.

The full record

Status note
Aligned has bought the land and says it is still planning. Amber dropped an annexation that would have brought the site under town zoning, and the county declined to create a planning commission.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)