Data center campus · Near NW 248th Street and Frisco Road, Piedmont, Canadian County, Oklahoma

Beltline Energy data center, Piedmont

Proposed as of Oct. 22, 2026

Beltline Energy is seeking a rezoning for a 321-acre data center in Piedmont, separate from Cloverleaf's nearby Project Open Sky.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyBeltline Energy data center, Piedmont · Proposed
PowerNot statedNot reported in the records found
Site321acres

Who is behind it

ProjectBeltline Energy data center, Piedmont
Developer and teamBeltline Energy
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Fox 25 reported the council had tabled Beltline's plan two weeks earlier and would take it up the following Monday. (KOKH Fox 25, Oct. 22, 2026)

  2. News 9 reported Piedmont's planning commission had sent the rezoning to the council, asking for developer-paid studies first. (News 9, Oct. 6, 2026)

  3. Investigate Midwest reported Beltline was proposing a 321-acre project in Piedmont. (Investigate Midwest, July 14, 2026)

Conflicts and open questions

  • Acreage from Investigate Midwest. Coordinates are approximate, near NW 248th Street and Frisco Road.

The full record

Status note
The planning commission advanced the rezoning in early October 2026. The council tabled it and set it for a meeting on Oct. 26.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.