Data center campus · NW 61st/62nd Streets and N. Lee Avenue, Oklahoma City, Oklahoma County, Oklahoma

Cerebras Oklahoma City (Scale Datacenter)

Operating as of Sept. 23, 2025

Cerebras opened a 10 MW AI inference site in September 2025 in a former Expand Energy building that Scale Datacenter bought and refitted. Also known as: former Chesapeake/Expand Energy data center.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyCerebras Oklahoma City (Scale Datacenter) · Operating · 10 MW
Power10MW reported · stated
Floor area82,000sq ft

Who is behind it

ProjectCerebras Oklahoma City (Scale Datacenter)Also: former Chesapeake/Expand Energy data center
Developer and teamScale Datacenter
End userCerebras Systems

The record, newest first

  1. Cerebras opened the 10 MW facility. (DCD, Sept. 23, 2025)

  2. Scale Datacenter was reported to have bought the building from Expand Energy. (DCD, May 31, 2025)

Conflicts and open questions

  • Reported sizes differ: 82,000 sq ft per CoStar vs. 56,250 sq ft in a Colliers brochure.

The full record

Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.