Data center campus · Near 2000 S. Council Road / SW 29th Street, southwest Oklahoma City, Oklahoma County, Oklahoma

CloudBurst Oklahoma City campus

Under construction as of Sept. 14, 2026

CloudBurst is building a three-data-center campus in southwest Oklahoma City, with groundbreaking set for the end of 2025 and about 200 MW planned by 2028.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyCloudBurst Oklahoma City campus · Under construction · 200 MW
Power200MW reported · stated

Who is behind it

ProjectCloudBurst Oklahoma City campus
Developer and teamCloudBurst
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. News 9 reported the campus under construction, with phase one expected at the end of 2026. (News 9, Sept. 14, 2026)

Conflicts and open questions

  • KGOU reported that OKC's May 2026 amendment exempted a facility near the OKC Outlet Mall, a few miles from this site. Whether that exemption is CloudBurst has not been confirmed.

The full record

Power note
News 9 printed '200W', which reads as 200 MW. Its phases add to only 80 MW: 30 MW (late 2026), 50 MW (mid-2027), with full power by the end of 2028. The gap is not explained.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)