Data center campus · Near 2000 S. Council Road / SW 29th Street, southwest Oklahoma City, Oklahoma County, Oklahoma
CloudBurst Oklahoma City campus
Under construction
as of Sept. 14, 2026
CloudBurst is building a three-data-center campus in southwest Oklahoma City, with groundbreaking set for the end of 2025 and about 200 MW planned by 2028.
Power200MW reported · stated
Who is behind it
ProjectCloudBurst Oklahoma City campus
Developer and teamCloudBurst
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
News 9 reported the campus under construction, with phase one expected at the end of 2026. (News 9, Sept. 14, 2026)
Conflicts and open questions
- KGOU reported that OKC's May 2026 amendment exempted a facility near the OKC Outlet Mall, a few miles from this site. Whether that exemption is CloudBurst has not been confirmed.
The full record
- Power note
- News 9 printed '200W', which reads as 200 MW. Its phases add to only 80 MW: 30 MW (late 2026), 50 MW (mid-2027), with full power by the end of 2028. The gap is not explained.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)