Data center campus · Fair Oaks Industrial Park, 11th Street and the west side of the Creek Turnpike, east Tulsa, Wagoner County, Oklahoma

Meta Tulsa data center (Project Anthem)

Under construction as of April 21, 2026

Meta's first Oklahoma data center, a $1 billion-plus AI campus on 340 acres in east Tulsa that broke ground in April 2026 after the city approved an 85% tax exemption in 2024. Also known as: Project Anthem, Atmoss LLC.

Cite← Oklahoma data centers
Adair CountyAlfalfa CountyAtoka CountyBeaver CountyBeckham CountyBlaine CountyBryan CountyCaddo CountyCanadian CountyCarter CountyCherokee CountyChoctaw CountyCimarron CountyCleveland CountyCoal CountyComanche CountyCotton CountyCraig CountyCreek CountyCuster CountyDelaware CountyDewey CountyEllis CountyGarfield CountyGarvin CountyGrady CountyGrant CountyGreer CountyHarmon CountyHarper CountyHaskell CountyHughes CountyJackson CountyJefferson CountyJohnston CountyKay CountyKingfisher CountyKiowa CountyLatimer CountyLe Flore CountyLincoln CountyLogan CountyLove CountyMajor CountyMarshall CountyMayes CountyMcClain CountyMcCurtain CountyMcIntosh CountyMurray CountyMuskogee CountyNoble CountyNowata CountyOkfuskee CountyOklahoma CountyOkmulgee CountyOsage CountyOttawa CountyPawnee CountyPayne CountyPittsburg CountyPontotoc CountyPottawatomie CountyPushmataha CountyRoger Mills CountyRogers CountySeminole CountySequoyah CountyStephens CountyTexas CountyTillman CountyTulsa CountyWagoner CountyWashington CountyWashita CountyWoods CountyWoodward CountyMeta Tulsa data center (Project Anthem) · Under construction
PowerNot statedNot reported in the records found
Site340acres

Who is behind it

ProjectMeta Tulsa data center (Project Anthem)Also: Project Anthem, Atmoss LLC
Developer and teamMeta (through Atmoss LLC)
End userMeta

The record, newest first

  1. Meta confirmed it is behind Project Anthem and announced the groundbreaking, citing about 1,000 peak construction jobs and 100 permanent jobs, with completion slated for 2028. (Meta, April 21, 2026; DatacenterDynamics, April 22, 2026; KJRH 2 News Oklahoma, April 22, 2026)

  2. Atmoss LLC withdrew its rezoning request for about 375 acres of phase two, between 11th and 21st streets east of 193rd East Avenue. (DatacenterDynamics, April 1, 2026; Public Radio Tulsa, April 22, 2026)

  3. The council adopted a citywide data center moratorium through Dec. 31, 2026, exempting both phases of Project Anthem. (Tulsa Flyer, March 25, 2026; KOKH FOX 25, March 26, 2026)

  4. The Tulsa City Council passed the ordinance creating the incentive district after its second public hearing. (Tulsa City Council, May 3, 2024)

  5. A council committee reviewed the request for a 25-year, 85% property tax exemption; the presenter did not name the company. (KJRH 2 News Oklahoma, April 17, 2024)

  6. DCD reported that the Tulsa Metropolitan Area Planning Commission had unanimously recommended the city's incentive project plan for an $800 million, 340-acre data center called Project Anthem. (DatacenterDynamics, March 8, 2024)

Conflicts and open questions

  • County is Wagoner based on DCD's tagging and the list of affected taxing entities (Wagoner County, Catoosa Public Schools); the site is inside Tulsa city limits.
  • Utility not confirmed from an opened source (Meta's post mentions a PSO customer program but does not name the serving utility); no MW figure found. Meta says it is adding 1,500 MW of clean energy in Oklahoma.
  • Infrastructure pledge reported as $25 million (Meta, KJRH) or $5 million (DCD).

The full record

Status note
Meta broke ground in April 2026 on the 340-acre first phase; the developer withdrew a rezoning request for a roughly 375-acre second phase on March 31, 2026.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.