Meta Tulsa data center (Project Anthem)
Meta's first Oklahoma data center, a $1 billion-plus AI campus on 340 acres in east Tulsa that broke ground in April 2026 after the city approved an 85% tax exemption in 2024. Also known as: Project Anthem, Atmoss LLC.
Who is behind it
The record, newest first
Meta confirmed it is behind Project Anthem and announced the groundbreaking, citing about 1,000 peak construction jobs and 100 permanent jobs, with completion slated for 2028. (Meta, April 21, 2026; DatacenterDynamics, April 22, 2026; KJRH 2 News Oklahoma, April 22, 2026)
Atmoss LLC withdrew its rezoning request for about 375 acres of phase two, between 11th and 21st streets east of 193rd East Avenue. (DatacenterDynamics, April 1, 2026; Public Radio Tulsa, April 22, 2026)
The council adopted a citywide data center moratorium through Dec. 31, 2026, exempting both phases of Project Anthem. (Tulsa Flyer, March 25, 2026; KOKH FOX 25, March 26, 2026)
The Tulsa City Council passed the ordinance creating the incentive district after its second public hearing. (Tulsa City Council, May 3, 2024)
A council committee reviewed the request for a 25-year, 85% property tax exemption; the presenter did not name the company. (KJRH 2 News Oklahoma, April 17, 2024)
DCD reported that the Tulsa Metropolitan Area Planning Commission had unanimously recommended the city's incentive project plan for an $800 million, 340-acre data center called Project Anthem. (DatacenterDynamics, March 8, 2024)
Conflicts and open questions
- County is Wagoner based on DCD's tagging and the list of affected taxing entities (Wagoner County, Catoosa Public Schools); the site is inside Tulsa city limits.
- Utility not confirmed from an opened source (Meta's post mentions a PSO customer program but does not name the serving utility); no MW figure found. Meta says it is adding 1,500 MW of clean energy in Oklahoma.
- Infrastructure pledge reported as $25 million (Meta, KJRH) or $5 million (DCD).
The full record
- Status note
- Meta broke ground in April 2026 on the 340-acre first phase; the developer withdrew a rezoning request for a roughly 375-acre second phase on March 31, 2026.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)