Data center project · Wasco County, Oregon
Google original 2006 data center rebuild, 4200 Columbia Road
Approved · Google's replacement of its first The Dalles data center with a new 77,000-square-foot building, approved by city staff in August 2026.
- Status
- Approved · as of Aug. 2026
- Location
- 4200 Columbia Road, Port of The Dalles · Wasco County
- Power
- Not reported
No power figure reported. - Floor area
- 77,000 sq ft
- Developer and team
- Google (through Design LLC)
- Incentives
- The original building ran under a 2005 enterprise zone abatement for 15 years and is now on the regular tax rolls ($4.7 million in 2025, as reported).
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Aug. 4, 2026 Columbia Community Connection reported The Dalles had approved the site plan administratively, with appeals open through Aug. 17. (Columbia Community Connection, Aug. 4, 2026)
- June 2025 Demolition permits were disclosed for the original building's equipment and slab. (Columbia Community Connection, Aug. 4, 2026)
Have records about this project? Send them to tips@signaldata.org.