Data center project · Crook County, Oregon
Meta Prineville data center campus
Operating · Meta's first company-owned data center campus, announced in Prineville in 2010, kept as operating context. Also known as: Facebook Prineville.
- Status
- Operating · as of May 9, 2024
- Location
- Off Tom McCall Road, Prineville · Crook County
- Power
- Not reported
No power figure from Meta in the sources reviewed. - Developer and team
- Meta
- Utility
- Pacific Power
- Water
- Meta paid for a second injection well for Prineville's aquifer storage and recovery system, which stores winter water for summer peaks driven partly by data center cooling (2024).
- Incentives
- The Bulletin reported in 2010 that the enterprise zone would excuse Facebook from up to about $2.8 million a year in local taxes; later agreements were not reviewed.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- May 9, 2024 The Bulletin reported Meta was funding a second aquifer injection well for the city. (The Bulletin (Bend), May 9, 2024)
- Jan. 22, 2010 The Bulletin reported Facebook had announced its first owned data center, on a 124-acre lot in Prineville, citing the enterprise zone as a key reason. (The Bulletin (Bend), Jan. 22, 2010)
Conflicts and open questions
- The 2026 renewal or expiry of Meta's Prineville tax agreements was not confirmed from a record or credited reporting.
Have records about this project? Send them to tips@signaldata.org.