Cielo Digital Infrastructure Gaffney campus
Texas-based Cielo Digital Infrastructure plans a $2.1 billion, four-building data center campus with its own substation on Ford Road in Gaffney, targeting first operations by the end of 2028.
Who is behind it
The record, newest first
A resident asked county council for clearer communication about the project; the county development board director said the site would be a data storage facility, not an AI center. (WSPA 7NEWS, Feb. 5, 2026)
Cherokee County Council finalized the incentive deal; the development board said terms would be public once paperwork was done. (SC Daily Gazette, June 25, 2025)
The governor's office announced Cielo's first South Carolina project: four buildings of about 400,000 sq ft each plus a substation, about $2.1 billion and 30 jobs. (Office of the Governor of South Carolina, June 24, 2025; WIS News 10, June 24, 2025)
Conflicts and open questions
- Square footage: four buildings of about 400,000 sq ft each per the state announcement (about 1.6 million sq ft total); one TV report described a 400,000 sq ft campus.
- The exact date of the council's final vote was not reported; reporting on June 25, 2025 said it came that week.
- Incentive amounts and term not found.
- Coordinates approximate, Ford Road area of Gaffney.
The full record
- Status note
- Cherokee County Council finalized an incentive agreement in June 2025; initial operations targeted for the end of 2028. No construction record found.
- Power note
- Up to 300 MW at full build-out, per the developer's website as reported; not stated in the state announcement.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)