Data center campus · International Technology and Aerospace Park, Myrtle Beach, Horry County, South Carolina

DC BLOX Myrtle Beach cable landing station

Operating as of Oct. 10, 2023

DC BLOX opened a cable landing station and data center in Myrtle Beach in 2023 that lands Google and Meta subsea cables, with room for up to five cables and about 125,000 sq ft at full build-out. Also known as: MYR1.

Cite← South Carolina data centers
Abbeville CountyAiken CountyAllendale CountyAnderson CountyBamberg CountyBarnwell CountyBeaufort CountyBerkeley CountyCalhoun CountyCharleston CountyCherokee CountyChester CountyChesterfield CountyClarendon CountyColleton CountyDarlington CountyDillon CountyDorchester CountyEdgefield CountyFairfield CountyFlorence CountyGeorgetown CountyGreenville CountyGreenwood CountyHampton CountyHorry CountyJasper CountyKershaw CountyLancaster CountyLaurens CountyLee CountyLexington CountyMarion CountyMarlboro CountyMcCormick CountyNewberry CountyOconee CountyOrangeburg CountyPickens CountyRichland CountySaluda CountySpartanburg CountySumter CountyUnion CountyWilliamsburg CountyYork CountyDC BLOX Myrtle Beach cable landing station · Operating · 19 MW
Power19MW reported · stated
Floor area125,000sq ft

Who is behind it

ProjectDC BLOX Myrtle Beach cable landing stationAlso: MYR1
Developer and teamDC BLOX
End userSubsea cable owners including Google (Firmina, Nuvem) and Meta (Anjana)

The record, newest first

  1. DC BLOX opened the facility, with three of five cable slots reserved for Google's Firmina and Nuvem and Meta's Anjana systems. (Data Center Dynamics, Oct. 10, 2023)

  2. DC BLOX announced a hurricane-hardened cable landing station at the Myrtle Beach technology park, connected to five pre-positioned subsea bore pipes. (DC BLOX, May 10, 2022)

Conflicts and open questions

  • Below the 50 MW floor; included as an operating site.
  • Square footage is the full build-out figure.
  • Coordinates approximate, technology park area in Myrtle Beach.

The full record

Power note
DC BLOX's 2022 announcement said up to 15 MW; 2023 reporting at opening said 19 MW.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.