Data center campus · Winding Woods Commerce Park, St. George, Dorchester County, South Carolina

Google St. George data center campus (Winding Woods Commerce Park)

Under construction as of Oct. 15, 2025

Google's second Dorchester County campus is going up on about 206 acres in the Winding Woods Commerce Park near St. George, land the county prepared under the code name Project Evergreen. Also known as: Project Evergreen, Gannett Enterprises LLC.

Cite← South Carolina data centers
Abbeville CountyAiken CountyAllendale CountyAnderson CountyBamberg CountyBarnwell CountyBeaufort CountyBerkeley CountyCalhoun CountyCharleston CountyCherokee CountyChester CountyChesterfield CountyClarendon CountyColleton CountyDarlington CountyDillon CountyDorchester CountyEdgefield CountyFairfield CountyFlorence CountyGeorgetown CountyGreenville CountyGreenwood CountyHampton CountyHorry CountyJasper CountyKershaw CountyLancaster CountyLaurens CountyLee CountyLexington CountyMarion CountyMarlboro CountyMcCormick CountyNewberry CountyOconee CountyOrangeburg CountyPickens CountyRichland CountySaluda CountySpartanburg CountySumter CountyUnion CountyWilliamsburg CountyYork CountyGoogle St. George data center campus (Winding Woods Commerce Park) · Under construction
PowerNot statedNot reported in the records found
Site206acres

Who is behind it

ProjectGoogle St. George data center campus (Winding Woods Commerce Park)Also: Project Evergreen, Gannett Enterprises LLC
Developer and teamGoogle (through Gannett Enterprises LLC)
End userGoogle

The record, newest first

  1. Google's $9 billion South Carolina announcement included completing the St. George campus. (ABC News 4 (WCIV), Oct. 13, 2025; Data Center Dynamics, Oct. 15, 2025)

  2. The state announced the Winding Woods campus as one of two new Google campuses in Dorchester County. (Office of Gov. Henry McMaster, Sept. 26, 2024; Data Center Dynamics, Sept. 27, 2024)

  3. Council adopted ordinances placing Gannett Enterprises LLC (formerly Project Evergreen) property in a joint county industrial park; Google said it had bought 206 acres near St. George for a possible later site. (Dorchester County Council, Feb. 15, 2024; Post and Courier, Feb. 15, 2024)

  4. Dorchester County Council authorized a development and water supply and sewer agreement with Gannett Enterprises LLC. (Dorchester County Council, Feb. 15, 2024)

Conflicts and open questions

  • In February 2024 Google said it planned to develop only Pine Hill for the time being; the state named Winding Woods as a campus in September 2024.
  • One October 2025 article dated the land purchase to 2025; earlier reporting and county records place it in early 2024.
  • Power provider and capacity not publicly reported.
  • Coordinates approximate, Winding Woods Commerce Park near St. George.

The full record

Status note
Groundbreaking was reported in September 2024; October 2025 reporting said construction was continuing.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)