Pollard data center site (McCormick)
McCormick County Council voted 3-2 to rezone about 1,000 acres of Pollard-owned forest near downtown McCormick for a natural gas-powered data center, after the planning commission had recommended denial, and voted down a proposed nine-month pause.
Who is behind it
The record, newest first
Council Chairman Bernie Hamby said he voted against the moratorium because Pollard Lumber Company said the matter had to be settled by September; the developer and end user were not named. (WRDW/WAGT News 12, Sept. 15, 2026)
County council approved the rezoning 3-2, rejected the proposed nine-month moratorium 3-2 on first reading and gave unanimous (5-0) first reading to a data center regulation ordinance. (WRDW/WAGT News 12, Sept. 10, 2026)
The planning commission recommended that council deny the rezoning, adopt a nine-month pause on data centers and write a data center ordinance; vote counts were not reported. (WRDW/WAGT News 12, July 30, 2026)
Pollard Lumber Company held an information session attended by nearly 400 people on the roughly 1,000-acre site; the company said a Kinder Morgan gas pipeline costing about $200 million to $280 million would be paid for entirely by the data center user. (WRDW/WAGT News 12, July 28, 2026)
Conflicts and open questions
- Pipeline cost reported as $200 million, as $200 million to $280 million and, in one article, as a $1.5 billion pipeline.
- The planning commission chair said the data center may not use all 1,000 acres.
- Reporting names Pollard Lumber Company as host of the information session and Pollard Land Company as the rezoning applicant.
- Coordinates approximate, Whitetown Road area of McCormick.
The full record
- Status note
- County council approved the rezoning 3-2 and rejected a proposed nine-month pause on data centers.
- Power note
- Not reported.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)