Data center campus · 771 Park Road, near Camden, Kershaw County, South Carolina

Terra Nexus Ventures data center (Park Road)

Withdrawn as of Oct. 6, 2025

A Charlotte-based developer sought to rezone 162 rural acres across from the Kershaw County landfill for a two-building data center, then withdrew the request in October 2025 after resident opposition.

Cite← South Carolina data centers
Abbeville CountyAiken CountyAllendale CountyAnderson CountyBamberg CountyBarnwell CountyBeaufort CountyBerkeley CountyCalhoun CountyCharleston CountyCherokee CountyChester CountyChesterfield CountyClarendon CountyColleton CountyDarlington CountyDillon CountyDorchester CountyEdgefield CountyFairfield CountyFlorence CountyGeorgetown CountyGreenville CountyGreenwood CountyHampton CountyHorry CountyJasper CountyKershaw CountyLancaster CountyLaurens CountyLee CountyLexington CountyMarion CountyMarlboro CountyMcCormick CountyNewberry CountyOconee CountyOrangeburg CountyPickens CountyRichland CountySaluda CountySpartanburg CountySumter CountyUnion CountyWilliamsburg CountyYork CountyTerra Nexus Ventures data center (Park Road) · Withdrawn
PowerNot statedNot reported in the records found
Site162acres

Who is behind it

ProjectTerra Nexus Ventures data center (Park Road)
Developer and teamTerra Nexus Ventures
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The developers withdrew the rezoning request before the council vote. (The Post and Courier, Oct. 6, 2025)

  2. Residents urged council to deny the rezoning, citing water, power and the lack of county data center rules; representatives described two server buildings with 10 to 15 workers. (WIS News 10, Sept. 23, 2025)

  3. The Kershaw County planning commission unanimously recommended rezoning the site from a rural district to general development. (Data Center Dynamics, Sept. 11, 2025; WIS News 10, Sept. 23, 2025)

Conflicts and open questions

  • Acreage reported as 161 or 162 acres.
  • No county council minutes found; status from reporting.
  • Coordinates approximate, Park Road area northeast of Camden.

The full record

Status note
The developer's attorney asked to withdraw the rezoning request before county council took it up.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.