Data center campus · Black Hills Industrial Center, near SD Highway 79 and Old Folsom Road, Rapid City, Pennington County, South Dakota
Sequitor Edge Rapid City
Proposed
as of Feb. 19, 2026
Sequitor Edge plans a Tier III edge colocation facility of about 30,000 square feet and an initial 2 MW on a 10-acre lot in Rapid City's Black Hills Industrial Center.
Power2MW reported · stated
Floor area30,000sq ft
Site10acres
Who is behind it
ProjectSequitor Edge Rapid City
Developer and teamSequitor Edge
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
Company outlined a 2 MW first phase that could grow to 10 MW and roughly 240 cabinets in the first hall. (Rapid City Post, Feb. 19, 2026)
Sequitor Edge, working with Elevate Rapid City, announced a 10-acre edge data center with three full-time jobs. (Rapid City Post, Feb. 12, 2026; KELOLAND, Feb. 13, 2026; Data Center Dynamics, Feb. 12, 2026)
Conflicts and open questions
- Coordinates approximate for the industrial center; no street address reported.
- DCD, citing local press, placed the site across Highway 16 from the Rapid City landfill, while a later Rapid City Post story placed it near Highway 79 and Old Folsom Road; the later local report is used.
The full record
- Status note
- Announced with Elevate Rapid City; site reportedly already zoned light industrial. No permits, construction start or timeline found.
- Power note
- About 2 MW for the first data hall, expandable to 10 MW with five halls.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)