Data center project · Stafford, Virginia
Accokeek Center data center campus
Approved · Stafford supervisors voted 4-3 to approve a 590,000 sq ft data center campus on 121 acres that does not fully meet the county's new 750-foot setback.
- Status
- Approved · as of Oct. 7, 2026
- Location
- Between Interstate 95 and U.S. 1, Falmouth District · Stafford
- Power
- 122 MW
Load requested for the campus, as presented by county staff; Dominion had issued no load letter. - Floor area
- 590,000 sq ft
- Land
- 121 acres
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 7, 2026 After a hearing that ran past 1 a.m., the board approved the project 4-3, using a provision that lets setbacks shrink when impacts are mitigated. (Fredericksburg Free Press, Oct. 8, 2026)
- Aug. 26, 2026 At a planning commission hearing that began Aug. 26 and ran past midnight, county staff said the campus would request 122 MW through one on-site substation and that Dominion had not issued a load letter; the commission recommended approval 4-3. (Potomac Local News, Sept. 1, 2026)
Conflicts and open questions
- The developer's attorney projected $13.5 million a year in county taxes; a supervisor questioned the figure. The developer is not named in the source opened.