Data center project · Culpeper, Virginia
Culpeper Technology Campus
Approved · A 155-acre, 600 MW campus approved in 2023 in the Culpeper Technology Zone; its substation passed the town's plan review in 2024.
- Status
- Approved · as of June 18, 2024
- Location
- Between Germanna Highway and McDevitt Drive, in the town and county · Culpeper
- Power
- 600 MW
Planned load as reported by InsideNoVa/Culpeper Times (Aug. 2024); no county or utility record of the figure was opened. - Floor area
- 2,000,000 sq ft
- Land
- 155 acres
- Developer and team
- STACK Infrastructure (owner)
- Utility
- Dominion Energy
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 2025 Dominion's proposed $253.7 million Culpeper transmission upgrade lists the campus, owned by STACK, among those it would serve. (Piedmont Environmental Council, Sept. 17, 2025)
- Aug. 15, 2024 Local reporting listed the 155-acre campus with a planned 600 MW load. (InsideNoVa / Culpeper Times, Aug. 15, 2024)
- June 18, 2024 The town planning commission found its substation location consistent with the comprehensive plan. (InsideNoVa / Culpeper Times, June 25, 2024)
- 2023 The rezoning was approved. (InsideNoVa / Culpeper Times, Aug. 15, 2024)
Have records about this project? Send them to tips@signaldata.org.