Data center project · Fauquier, Virginia
Remington Digital Campus (Gigaland)
Withdrawn · A Remington data center campus that shrank from 2.2 million to about 1 million sq ft and was withdrawn twice, in August 2025 and again in August 2026. Also known as: Gigaland.
- Status
- Withdrawn · as of Aug. 17, 2026
- Location
- Near Remington, next to the Meadows housing development · Fauquier
- Status note
- Withdrawn a second time on Aug. 17, 2026, weeks before a scheduled Board of Supervisors vote.
- Power
- 600 MW
Two substations needing 600 MW in the 2025 resubmission; the 2024 plan had four substations and 1.2 GW. - Floor area
- 998,662 sq ft
Cut from about 2.22 million sq ft (2024) to 998,662 sq ft (2025 filing); an August 2025 preview gave 847,400 sq ft. - Land
- 200 acres
- Investment
- About $3.07 billion (developer estimate)
- Developer and team
- Gigaland (applicant Lucky Hill LLC)
- End user
- Equinix was assumed to be the end user, according to county staff
- Utility
- Dominion Energy
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 17, 2026 Gigaland withdrew the application again ahead of a Sept. 10 board meeting. (FauquierNow, Sept. 17, 2026)
- Dec. 18, 2025 The developers said they would refile a smaller plan: six buildings, two substations, 600 MW and projected county revenue of about $42.75 million a year by 2036. (FauquierNow, Dec. 18, 2025)
- Aug. 25, 2025 The developers withdrew the 2024 applications, canceling a Sept. 11 supervisors' hearing. (FauquierNow, Aug. 25, 2025)