Data center project · Fauquier, Virginia
Remington Innovation Campus
Withdrawn · A six-building, three-substation campus on 210.7 acres near Remington, withdrawn hours before its planning commission work session.
- Status
- Withdrawn · as of Sept. 17, 2026
- Location
- Remington area · Fauquier
- Power
- Not reported
The withdrawn application called for three substations; no power figure was found. - Land
- 210.7 acres
- Developer and team
- SDC Capital Partners (financing the applicants)
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 17, 2026 The applicants asked the county to withdraw the comprehensive plan amendment, rezoning and substation requests the morning of the commission session. (FauquierNow, Sept. 17, 2026)
Conflicts and open questions
- The applicants for the 11 parcels included Lee District Supervisor Daron Culbertson, who owns some of the land.
- A third Remington-area proposal, Convergent Technology Park (Convergent VA, LLC), was withdrawn in late August 2026; it is not listed separately because no size was found.
Have records about this project? Send them to tips@signaldata.org.